5831 W 78TH PL 90045
Certificate Information: 5831 W 78TH PL 90045
- Application / Permit
- 20010-10000-04065
- Plan Check / Job No.
- B20LA20298
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ADU DETACHED PER ORDINANCE 1 OF 2
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | CARLOS MONTES |
| Corrections Issued | 1/15/2021 | CARLOS MONTES |
| Quality Review Completed | 2/1/2021 | WING SUEN |
| Applicant returned to address corrections | 7/2/2021 | CARLOS MONTES |
| Plan Check Approved | 7/22/2021 | CARLOS MONTES |
| Issued | 8/18/2021 | APPLICANT |
| Building Plans Picked Up | 8/25/2021 | APPLICANT |
| CofO in Progress | 1/9/2024 | BOBBY KEY |
| Permit Finaled | 1/17/2024 | DANIEL ORRANTE |
| CofO Issued | 1/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2021 | DINAH GARIN |
| ZA Case | Cleared | 3/9/2021 | JOE LUCKEY |
| Specific Plan | Cleared | 3/15/2021 | PETE EYRE |
| Hydrant and Access approval | Cleared | 4/24/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 6/8/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/14/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 7/2/2021 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 7/2/2021 | CARLOS MONTES |
| Construction near power lines | Cleared | 7/6/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Coatto Construction Management Inc; Lic. No.: 1029966-B | 8031 MAIN ST STANTON, CA 90680 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/5/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/24/2022 | Approved | BOBBY KEY |
| Insulation | 5/24/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 8/25/2022 | Partial Inspection | BOBBY KEY |
| Deputy Wood Construction | 10/4/2022 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/2/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 2/2/2023 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 2/2/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 2/2/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 2/2/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/2/2023 | Not Ready for Inspection | BOBBY KEY |
| Verify Sprinkler Sign Off | 2/2/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/8/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 2/8/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/8/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/28/2023 | Conditional Approval | HERBERT GIRON |
| Final | 2/28/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 2/28/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 3/30/2023 | Approved | BOBBY KEY |
| Shower Pan | 4/19/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/12/2023 | Corrections Issued | BOBBY KEY |
| Final | 9/12/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/12/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/12/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/12/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 9/12/2023 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 9/12/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 9/13/2023 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Final | 12/28/2023 | No Access for Inspection | BOBBY KEY |
| HVAC-Final | 12/28/2023 | No Access for Inspection | BOBBY KEY |
| PLUMBING-Final | 12/28/2023 | No Access for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 12/29/2023 | Approved | BOBBY KEY |
| Final | 12/29/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 12/29/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 12/29/2023 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 12/29/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 1/8/2024 | OK to Issue CofO | BOBBY KEY |
| PLUMBING-Final | 1/8/2024 | Approved | BOBBY KEY |
| Service/Power Release | 1/8/2024 | Approved | BOBBY KEY |