5909-5911 N FAIR AVE 91601

Certificate Information: 5909-5911 N FAIR AVE 91601

Application / Permit
20010-10000-04045
Plan Check / Job No.
B20LA20215
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (2) DETACHED ADU UNITS @ REAR PARKING AREA OF EXISTING MULTI FAMILY BUILDING. GOVT CODE 65852.2 (E)(1)(D) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2021 FERNANDO FLORES
Corrections Issued 1/12/2021 FERNANDO FLORES
Quality Review Completed 1/19/2021 STANLEY RAAP
Plan Check Approved 1/21/2022 FERNANDO FLORES
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/9/2022 APPLICANT
CofO in Progress 2/3/2023 JOHN KITCKO
CofO Issued 2/15/2023 RICKEY JACKSON
Permit Finaled 2/15/2023 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 2/1/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/4/2021 GABRIEL ROBLES
Sewer availability Cleared 2/4/2021 GABRIEL ROBLES
Certificate of Compliance Cleared 3/25/2021 JOE LUCKEY
Frnt yard landscape/Water mgmt Cleared 3/25/2021 JOE LUCKEY
Hydrant and Access approval Cleared 4/15/2021 KURT CORRAL
Construction near power lines Cleared 5/25/2021 RIDWAN HARDY
Highway dedication Cleared 12/9/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/9/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Rent Ready Construction Inc; Lic. No.: 1065376-B 631 N SIERRA BONITA AVE      LOS ANGELES, CA 90036
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/26/2022 Conditional Approval JOHN KITCKO
Green Building Rough 6/6/2022 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/6/2022 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/6/2022 Partial Approval JOHN KITCKO
Insulation 6/10/2022 Partial Approval JOHN KITCKO
Deputy Wood Construction 7/1/2022 Approved JOHN KITCKO
Green Building Rough 7/13/2022 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 7/13/2022 Not Ready for Inspection ROBERT DAVIS
Wood Frame 7/13/2022 Corrections Issued ROBERT DAVIS
Green Building Rough 7/19/2022 Approved JOHN KITCKO
Verify Sprinkler Sign Off 7/19/2022 Approved JOHN KITCKO
Wood Frame 7/19/2022 Not Ready for Inspection JOHN KITCKO
Insulation 7/28/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 7/28/2022 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 7/29/2022 Approved JOHN KITCKO
Drywall Nailing 8/5/2022 Conditional Approval JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Not Ready JOHN KITCKO
Pre-Inspection 11/15/2022 Partial Inspection JOHN KITCKO
Final 1/31/2023 OK to Issue CofO JOHN KITCKO
Footing/Foundation/Slab 1/31/2023 Approved JOHN KITCKO
Green Building Final 1/31/2023 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved JOHN KITCKO
Smoke Detectors 1/31/2023 Approved JOHN KITCKO
Special/Order Compliance 1/31/2023 Approved BRIAN KELLY
Wood Frame 1/31/2023 Approved JOHN KITCKO