1757 W 35TH PL 90018
Certificate Information: 1757 W 35TH PL 90018
- Application / Permit
- 20010-10000-04028
- Plan Check / Job No.
- B20LA20143
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU WITH NEW ATTACHED GARAGE
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 11/12/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/24/2020 | WING SUEN |
| Plan Check Approved | 2/14/2022 | CRYSTEL MAALOUF |
| Issued | 3/15/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| CofO in Progress | 5/29/2024 | SABAS ALONSO |
| CofO Issued | 6/3/2024 | DEROLD HAUFF |
| Permit Finaled | 6/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/15/2020 | CELINA MORENO |
| Construction near power lines | Cleared | 3/30/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/1/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/28/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | KHOUNG LE |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/28/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/15/2022 | Partial Approval | SABAS ALONSO |
| METHANE-Barrier | 9/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 9/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 11/1/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 11/9/2022 | Approved | SABAS ALONSO |
| METHANE-Barrier | 11/9/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 3/3/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 3/3/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 3/3/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 3/3/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/13/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Approved | SABAS ALONSO |
| METHANE-Rough | 4/13/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/13/2023 | Approved | SABAS ALONSO |
| Insulation | 4/20/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/28/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/15/2023 | Partial Approval | SABAS ALONSO |
| Final | 12/20/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/20/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/20/2023 | Approved | SABAS ALONSO |
| Final | 4/4/2024 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 4/4/2024 | No Access for Inspection | SABAS ALONSO |
| Final | 5/17/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | SABAS ALONSO |
| Final | 5/28/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 5/28/2024 | Approved | SABAS ALONSO |