1757 W 35TH PL 90018

Certificate Information: 1757 W 35TH PL 90018

Application / Permit
20010-10000-04028
Plan Check / Job No.
B20LA20143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU WITH NEW ATTACHED GARAGE
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
CofO Issued on 6/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 CRYSTEL MAALOUF
Corrections Issued 11/12/2020 CRYSTEL MAALOUF
Quality Review Completed 11/24/2020 WING SUEN
Plan Check Approved 2/14/2022 CRYSTEL MAALOUF
Issued 3/15/2022 APPLICANT
Building Plans Picked Up 3/21/2022 APPLICANT
CofO in Progress 5/29/2024 SABAS ALONSO
CofO Issued 6/3/2024 DEROLD HAUFF
Permit Finaled 6/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/10/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/15/2020 CELINA MORENO
Sewer availability Cleared 12/15/2020 CELINA MORENO
Construction near power lines Cleared 3/30/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 5/1/2021 JOHN CONNEALLY
Low Impact Development Cleared 12/28/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/3/2022 KHOUNG LE

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/28/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/15/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 9/15/2022 Partial Approval SABAS ALONSO
METHANE-Barrier 9/15/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 9/15/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 11/1/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 11/9/2022 Approved SABAS ALONSO
METHANE-Barrier 11/9/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 3/3/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval SABAS ALONSO
Green Building Rough 3/3/2023 Approved SABAS ALONSO
HVAC-Rough 3/3/2023 Approved SABAS ALONSO
PLUMBING-Rough 3/3/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 4/13/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Approved SABAS ALONSO
METHANE-Rough 4/13/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/13/2023 Approved SABAS ALONSO
Insulation 4/20/2023 Approved SABAS ALONSO
Drywall Nailing 4/28/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 5/15/2023 Partial Approval SABAS ALONSO
Final 12/20/2023 Corrections Issued SABAS ALONSO
Green Building Final 12/20/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/20/2023 Approved SABAS ALONSO
Final 4/4/2024 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 4/4/2024 No Access for Inspection SABAS ALONSO
Final 5/17/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Approved SABAS ALONSO
Final 5/28/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 5/28/2024 Approved SABAS ALONSO