3661 N ARMOUR AVE 90032

Certificate Information: 3661 N ARMOUR AVE 90032

Application / Permit
20010-10000-04027
Plan Check / Job No.
B20LA20123
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33
Permit Issued
Issued on 11/29/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 DANIEL YIP
Corrections Issued 11/30/2020 DANIEL YIP
Quality Review Completed 12/9/2020 ALLEN MANALANSAN
Building Plans Picked Up 12/29/2020 APPLICANT
Applicant returned to address corrections 10/25/2023 DANIEL YIP
Applicant returned to address corrections 11/20/2023 DANIEL YIP
Plan Check Approved 11/22/2023 DANIEL YIP
Issued 11/29/2023 APPLICANT
CofO in Progress 5/29/2025 LILIANA PORTILLO
Permit Finaled 6/5/2025 DEROLD HAUFF
CofO Issued 6/5/2025 DEROLD HAUFF
Permit Finaled 6/5/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/12/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 3/12/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/15/2021 JEANIE LAM
Hydrant and Access approval Cleared 4/24/2021 KURT CORRAL
Address approval Cleared 2/22/2022 JEANIE LAM
Sewer availability Cleared 2/24/2022 JEANIE LAM
Grading Pre-Inspection Cleared 3/10/2022 VASIL MIHALEV
"D" conditions Cleared 3/9/2023 ANACANY HURTADO
"Q" conditions Cleared 3/9/2023 ANACANY HURTADO
ZI Cleared 3/9/2023 ANACANY HURTADO
Low Impact Development Cleared 5/1/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/2/2023 JEANIE LAM
GPI Written Notices Cleared 11/22/2023 DANIEL YIP

Contact Information

Contractor G A Design Build; Lic. No.: 941130-B 8449 EVEREST ST      DOWNEY, CA 90242
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2023 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Corrections Issued LILIANA PORTILLO
Gas Test 2/16/2024 Approved LILIANA PORTILLO
HVAC-Rough 2/16/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/16/2024 Approved LILIANA PORTILLO
Underground Mechanical 2/16/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 3/11/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 3/11/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready LILIANA PORTILLO
Verify Sprinkler Sign Off 3/11/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 3/21/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 3/21/2024 Partial Approval LILIANA PORTILLO
Insulation 3/26/2024 Not Ready for Inspection LILIANA PORTILLO
Wood Frame 3/26/2024 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 3/27/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 4/2/2024 Approved BRENDAN MORELLI
Green Building Rough 4/2/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 4/9/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Approved LILIANA PORTILLO
Insulation 4/9/2024 Corrections Issued LILIANA PORTILLO
Drywall Nailing 4/18/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/18/2024 Approved LILIANA PORTILLO
Shower Pan 4/18/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/5/2024 Not Ready for Inspection LILIANA PORTILLO
Final 7/5/2024 Corrections Issued LILIANA PORTILLO
Gas Test 7/5/2024 Approved LILIANA PORTILLO
HVAC-Final 7/5/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 7/5/2024 Not Ready for Inspection LILIANA PORTILLO
Final 5/22/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/22/2025 Approved LILIANA PORTILLO
Green Building Final 5/22/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 5/22/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/22/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/28/2025 Approved LILIANA PORTILLO
Final 5/28/2025 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 5/28/2025 Approved LILIANA PORTILLO
PLUMBING-Final 5/28/2025 Approved LILIANA PORTILLO
Service/Power Release 5/28/2025 Approved LILIANA PORTILLO