6578 S 2ND AVE 90043

Certificate Information: 6578 S 2ND AVE 90043

Application / Permit
20010-10000-04020
Plan Check / Job No.
B20LA20093
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACH ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A 33(c) AND (d). ALL WORK PER TYPE V SHEET.
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 3/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/16/2020 FARSHAD ALIMOHAMADI
Corrections Issued 11/16/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/27/2021 RAHEL BEYENE
Applicant returned to address corrections 8/9/2021 FERNANDO FLORES
Plan Check Approved 9/9/2021 DANIEL SANJUAN
Issued 9/20/2021 APPLICANT
Building Plans Picked Up 9/27/2021 APPLICANT
CofO in Progress 3/7/2023 ENRIQUE MIRELES
Permit Finaled 3/11/2023 DEROLD HAUFF
CofO Issued 3/11/2023 DEROLD HAUFF
Permit Finaled 3/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/4/2021 THOMAS LANG
Sewer availability Cleared 2/4/2021 THOMAS LANG
Low Impact Development Cleared 4/8/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 4/12/2021 THOMAS LANG
Construction near power lines Cleared 6/29/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2021 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/24/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 11/24/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/8/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 12/8/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 12/8/2021 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 12/8/2021 Approved FREDDIE RIVERA
Insulation 12/9/2021 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 12/9/2021 Partial Approval FREDDIE RIVERA
Insulation 12/10/2021 No Access for Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 1/24/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/24/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Approved FREDDIE RIVERA
Gas Test 1/24/2022 Approved FREDDIE RIVERA
Green Building Rough 1/24/2022 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 1/24/2022 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 1/24/2022 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 1/24/2022 Not Ready for Inspection FREDDIE RIVERA
Wood Frame 1/24/2022 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 1/25/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/25/2022 Approved FREDDIE RIVERA
Green Building Rough 1/25/2022 Approved FREDDIE RIVERA
HVAC-Rough 1/25/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 1/25/2022 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 1/25/2022 Not Ready for Inspection FREDDIE RIVERA
Insulation 2/7/2022 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 2/7/2022 Corrections Issued SHAVONNE ESPINOZA
Sewer 2/8/2022 Not Ready for Inspection FREDDIE RIVERA
Underground Mechanical 2/8/2022 Approved FREDDIE RIVERA
Insulation 2/10/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Sewer 2/25/2022 Approved LILIANA PORTILLO
Insulation 3/16/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/16/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/21/2022 Approved ENRIQUE MIRELES
Drywall Nailing 3/24/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/24/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/23/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 5/23/2022 Corrections Issued ANTHONY EGSON
Final 5/23/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 5/23/2022 Approved ANTHONY EGSON
Green Building Rough 5/23/2022 Approved ANTHONY EGSON
HVAC-Final 5/23/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 5/23/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Not Ready ANTHONY EGSON
Service/Power Release 5/23/2022 Corrections Issued ANTHONY EGSON
Smoke Detectors 5/23/2022 Approved ANTHONY EGSON
Final 7/6/2022 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/6/2022 Approved ENRIQUE MIRELES
Final 2/14/2023 Corrections Issued ENRIQUE MIRELES
Final 2/23/2023 Corrections Issued ENRIQUE MIRELES
Final 3/6/2023 OK to Issue CofO ENRIQUE MIRELES