438 N LA JOLLA AVE 90048
Certificate Information: 438 N LA JOLLA AVE 90048
- Application / Permit
- 20010-10000-03995
- Plan Check / Job No.
- B20LA20001
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO-STORY 2,820.24-SF, SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 12/1/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/10/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 3/31/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/26/2021 | SERGIO GUTIERREZ |
| Issued | 6/24/2021 | APPLICANT |
| Building Plans Picked Up | 6/25/2021 | APPLICANT |
| CofO in Progress | 7/5/2024 | AMIR NAZARIAN |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 1/19/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 2/12/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 3/10/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/10/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/10/2021 | JEANIE LAM |
| Stormwater Pollution Mitigatn | Cleared | 3/10/2021 | MARTIN FRAGOSO |
Contact Information
| Architect | Baron,, Gabriel; Lic. No.: C38679 | 4619 SANTA LUCIA DR WOODLAND HILLS, CA 91364 |
| Contractor | Baron Gabriel; Lic. No.: 710011-B | 4619 SANTA LUCIA DR WOODLAND HILLS, CA 91364 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 9/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 9/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 9/8/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 9/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 9/23/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Methane Barrier | 9/30/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Methane Barrier | 10/1/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/6/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 10/6/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Steel/Welding | 10/27/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/10/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 6/6/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/14/2022 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 6/14/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/16/2022 | Approved | ADAM ESCOTO |
| HVAC-Rough | 6/27/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 7/18/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/19/2022 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 7/19/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 7/19/2022 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 7/19/2022 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/19/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/23/2022 | Approved | MICHAEL LEWIS |
| Insulation | 8/26/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 9/22/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/29/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 1/30/2024 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 1/30/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/2/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 2/2/2024 | Approved | LILIANA PORTILLO |
| Service/Power Release | 2/2/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/13/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 3/14/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 3/14/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 3/27/2024 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/23/2024 | Conditional Approval | JEFFREY MEAD |
| Final | 4/23/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 4/23/2024 | Corrections Issued | JEFFREY MEAD |
| METHANE-Final | 4/23/2024 | Conditional Approval | JEFFREY MEAD |
| METHANE-Rough | 4/23/2024 | Conditional Approval | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/23/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/15/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 5/15/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 5/15/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Final | 5/15/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 5/15/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 6/3/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 6/3/2024 | Partial Inspection | AMIR NAZARIAN |
| HVAC-Final | 6/3/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Final | 6/3/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Rough | 6/3/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 6/14/2024 | Conditional Approval | AMIR NAZARIAN |
| Final | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Final | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Rough | 6/14/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 6/26/2024 | Approved | RICHARD DOCKUS |
| Final | 6/26/2024 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 6/26/2024 | Approved | RICHARD DOCKUS |
| METHANE-Final | 6/26/2024 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 6/26/2024 | Approved | RICHARD DOCKUS |
| Final | 7/1/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Gas Test | 7/1/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 7/3/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Gas Test | 7/3/2024 | Approved | AMIR NAZARIAN |