2829 N VAQUERO AVE 90032
Certificate Information: 2829 N VAQUERO AVE 90032
- Application / Permit
- 20010-10000-03991
- Plan Check / Job No.
- B20LA19976
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU PER PER 12.22 A33 C & D
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- Issued on 1/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | STARR CHEN |
| Corrections Issued | 12/5/2020 | STARR CHEN |
| Building Plans Picked Up | 12/22/2020 | APPLICANT |
| Quality Review Completed | 6/24/2021 | JASON HEALEY |
| Applicant returned to address corrections | 6/24/2021 | STARR CHEN |
| Applicant returned to address corrections | 10/29/2021 | STARR CHEN |
| Plan Check Approved | 12/7/2021 | STARR CHEN |
| No Progress | 12/30/2021 | STARR CHEN |
| Plan Check Approved | 12/30/2021 | STARR CHEN |
| Issued | 1/14/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/11/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/3/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/20/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 5/18/2021 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 12/7/2021 | STARR CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: C43117 | 9234 STAMPS AVE DOWNEY, CA 90240 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2022 | Partial Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Corrections Issued | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Partial Approval | AMY COLIN |
| Drywall Nailing | 9/12/2022 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 10/17/2022 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 10/17/2022 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 11/7/2022 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 11/7/2022 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 11/7/2022 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 11/8/2022 | Approved | AMY COLIN |
| HVAC-Rough | 11/8/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/8/2022 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 11/8/2022 | Approved | AMY COLIN |
| Wood Frame | 11/8/2022 | Partial Approval | AMY COLIN |
| Insulation | 11/17/2022 | Corrections Issued | AMY COLIN |
| Drywall Nailing | 11/28/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/6/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 3/13/2023 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | AMY COLIN |
| Final | 7/10/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 7/10/2023 | Approved | AMY COLIN |
| Green Building Final | 7/10/2023 | Approved | AMY COLIN |
| Green Building Rough | 7/10/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 7/10/2023 | Approved | AMY COLIN |
| Smoke Detectors | 7/10/2023 | Corrections Issued | AMY COLIN |
| Verify Sprinkler Sign Off | 7/10/2023 | Approved | AMY COLIN |
| Final | 5/28/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 5/28/2024 | Corrections Issued | LILIANA PORTILLO |
| Final | 3/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 3/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |