11789 N GLENCREST DR 91340
Certificate Information: 11789 N GLENCREST DR 91340
- Application / Permit
- 20010-10000-03990
- Plan Check / Job No.
- B20LA19973
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. NEW 1 STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d) "COMPLY WITH DEPARTMENT ORDER effective date 02/19/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/12/2022
- Issuing Office
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 12/4/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/29/2020 | WING SUEN |
| Applicant returned to address corrections | 4/7/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/9/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/8/2022 | CRYSTEL MAALOUF |
| Issued | 6/12/2022 | APPLICANT |
| CofO in Progress | 5/21/2024 | MICHEL ABAJAN |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
| CofO Issued | 6/21/2024 | RUBEN SALAS |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 12/15/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 12/23/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/8/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/23/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/18/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Hold | Cleared | 6/22/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 6/30/2022 | No Access for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | No Access for Inspection | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 7/7/2022 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/18/2023 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/1/2023 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/10/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/2/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/3/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | No Access for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 4/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 4/13/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/13/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/19/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/19/2023 | Approved | MICHEL ABAJAN |
| Insulation | 4/28/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/8/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/8/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 5/10/2023 | No Access for Inspection | ARAM AVEDISIAN |
| Shower Pan | 5/31/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/28/2023 | No Access for Inspection | MICHEL ABAJAN |
| Final | 7/28/2023 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 7/28/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/28/2023 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 7/28/2023 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 7/28/2023 | No Access for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/30/2023 | No Access for Inspection | MISAEL ESPARZA |
| Gas Test | 10/30/2023 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 10/30/2023 | No Access for Inspection | MISAEL ESPARZA |
| Sewer | 10/30/2023 | No Access for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 12/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 12/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 1/10/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/14/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/10/2024 | Approved | MICHEL ABAJAN |
| Final | 5/10/2024 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 5/10/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/10/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 5/10/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 5/10/2024 | Approved | MICHEL ABAJAN |
| Final | 5/21/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 5/21/2024 | Approved | MICHEL ABAJAN |