11789 N GLENCREST DR 91340

Certificate Information: 11789 N GLENCREST DR 91340

Application / Permit
20010-10000-03990
Plan Check / Job No.
B20LA19973
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. NEW 1 STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d) "COMPLY WITH DEPARTMENT ORDER effective date 02/19/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 6/12/2022
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 CRYSTEL MAALOUF
Corrections Issued 12/4/2020 CRYSTEL MAALOUF
Quality Review Completed 12/29/2020 WING SUEN
Applicant returned to address corrections 4/7/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 5/9/2022 CRYSTEL MAALOUF
Plan Check Approved 6/8/2022 CRYSTEL MAALOUF
Issued 6/12/2022 APPLICANT
CofO in Progress 5/21/2024 MICHEL ABAJAN
Permit Finaled 6/21/2024 RUBEN SALAS
CofO Issued 6/21/2024 RUBEN SALAS
Permit Finaled 6/21/2024 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 12/15/2020 MIGUEL GAMBOA
Address approval Cleared 12/23/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/28/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/8/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 3/23/2021 JOHN CONNEALLY
Low Impact Development Cleared 11/18/2021 TA ANH
Roof/Waste drainage to street Cleared 1/18/2022 JOSE DUARTE-DIAZ
Hold Cleared 6/22/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 6/30/2022 No Access for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 No Access for Inspection ROBERT GOLD
Excavation/Setback/Form/Re-Bar 7/6/2022 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 7/7/2022 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 1/18/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 2/1/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 2/10/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 3/2/2023 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 3/3/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/13/2023 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 4/13/2023 Not Ready for Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 4/13/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/13/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/19/2023 Approved MICHEL ABAJAN
Green Building Rough 4/19/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/19/2023 Approved MICHEL ABAJAN
Insulation 4/28/2023 Approved MICHEL ABAJAN
Drywall Nailing 5/8/2023 Approved MICHEL ABAJAN
Shower Pan 5/8/2023 Approved MICHEL ABAJAN
Underground Mechanical 5/10/2023 No Access for Inspection ARAM AVEDISIAN
Shower Pan 5/31/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/28/2023 No Access for Inspection MICHEL ABAJAN
Final 7/28/2023 No Access for Inspection MICHEL ABAJAN
Green Building Final 7/28/2023 Approved MICHEL ABAJAN
HVAC-Final 7/28/2023 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 7/28/2023 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 7/28/2023 No Access for Inspection MICHEL ABAJAN
Smoke Detectors 7/28/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 10/30/2023 No Access for Inspection MISAEL ESPARZA
Gas Test 10/30/2023 No Access for Inspection MISAEL ESPARZA
PLUMBING-Final 10/30/2023 No Access for Inspection MISAEL ESPARZA
Sewer 10/30/2023 No Access for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/8/2023 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 12/8/2023 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 1/10/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 2/14/2024 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 5/10/2024 Approved MICHEL ABAJAN
Final 5/10/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 5/10/2024 Approved MICHEL ABAJAN
PLUMBING-Final 5/10/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 5/10/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 5/10/2024 Approved MICHEL ABAJAN
Final 5/21/2024 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 5/21/2024 Approved MICHEL ABAJAN