641 E 25TH ST 90011
Certificate Information: 641 E 25TH ST 90011
- Application / Permit
- 20010-10000-03981
- Plan Check / Job No.
- B20LA19932
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan: NEW 1 STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 12/3/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/28/2020 | WING SUEN |
| Applicant returned to address corrections | 4/6/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/14/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 11/2/2021 | CRYSTEL MAALOUF |
| Issued | 11/10/2021 | APPLICANT |
| CofO in Progress | 8/2/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 8/30/2022 | DEROLD HAUFF |
| CofO Issued | 8/30/2022 | DEROLD HAUFF |
| Permit Finaled | 8/30/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/17/2020 | CECILIO NAVARRO |
| Highway dedication | Cleared | 3/15/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 4/24/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 9/12/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/20/2021 | JEANIE LAM |
Contact Information
| Contractor | G A Design Build; Lic. No.: 941130-B | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: NA77737 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 12/2/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/9/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/14/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/16/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/18/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/18/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 1/18/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 2/2/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 2/2/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/2/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 2/2/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 2/2/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 2/8/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/8/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/29/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 6/29/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/25/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/25/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 7/28/2022 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 7/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 8/2/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/2/2022 | Approved | JOAQUIN GREENOUGH |