4805 N MATILIJA AVE #2 91423
Certificate Information: 4805 N MATILIJA AVE #2 91423
- Application / Permit
- 20010-10000-03962
- Plan Check / Job No.
- B20LA19795
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SFD ATTACHED 2 CAR GARAGE PER SMALL LOT SUBDIVISION. BUILDING 2 OF 4.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | DANIEL YIP |
| Corrections Issued | 12/4/2020 | DANIEL YIP |
| Quality Review Completed | 12/9/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
| Applicant returned to address corrections | 1/27/2022 | DANIEL YIP |
| Plan Check Approved | 6/8/2022 | DANIEL YIP |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 1/13/2025 | MISAEL ESPARZA |
| No Progress | 2/13/2025 | JUAN VALENZUELA |
| CofO in Progress | 2/13/2025 | JUAN VALENZUELA |
| CofO in Progress | 2/13/2025 | JUAN VALENZUELA |
| CofO in Progress | 4/3/2025 | JUAN VALENZUELA |
| Permit Finaled | 4/4/2025 | RUBEN SALAS |
| CofO Issued | 4/4/2025 | RUBEN SALAS |
| Permit Finaled | 4/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/7/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/2/2021 | JOHN CONNEALLY |
| "Q" conditions | Cleared | 6/1/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 6/1/2021 | MIGUEL GAMBOA |
| Trees in Parkway | Cleared | 7/8/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 12/29/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/17/2022 | ANDRES COVARRUBIAS |
| Frnt yard landscape/Water mgmt | Cleared | 3/18/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 3/18/2022 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | CARLOS AGUILERA |
| Excavation more than 5-ft deep | Cleared | 4/15/2022 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 4/18/2022 | BRANDON WILSON |
| Highway dedication | Cleared | 5/19/2022 | LEE GUILBEAUX |
| Permit | Cleared | 5/19/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Piling/Pier/Caisson | 7/18/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/24/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 8/25/2022 | Conditional Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 9/6/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/13/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/20/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 9/28/2022 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/28/2022 | Approved | MISAEL ESPARZA |
| Deputy Steel/Welding | 10/11/2022 | Conditional Approval | CALEB MEISTER |
| Deputy Steel/Welding | 10/17/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 10/21/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 10/27/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | No Access for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | No Access for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 11/15/2022 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 11/23/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Steel/Welding | 12/1/2022 | Conditional Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 12/6/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 12/21/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 2/3/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 2/3/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/17/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 2/17/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/22/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 2/22/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/13/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 3/13/2023 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Rough | 3/13/2023 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/13/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 3/31/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/6/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 4/6/2023 | Approved | MISAEL ESPARZA |
| Insulation | 4/7/2023 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 4/18/2023 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 4/18/2023 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/21/2023 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 4/27/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 5/3/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 5/3/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/22/2023 | Partial Approval | DAVID MATSON |
| Insulation | 5/22/2023 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 5/30/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Drywall Nailing | 6/7/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 9/29/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 11/13/2023 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 11/13/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 11/14/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 11/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/20/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 11/20/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 11/22/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/28/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/30/2023 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/10/2024 | Approved | MISAEL ESPARZA |
| Final | 12/27/2024 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/27/2024 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 12/27/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2024 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/27/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/7/2025 | Approved | MISAEL ESPARZA |
| Final | 1/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 1/7/2025 | Approved | MISAEL ESPARZA |
| Structural Steel Frame | 1/7/2025 | Partial Inspection | MISAEL ESPARZA |
| Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Structural Steel Frame | 1/9/2025 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 2/13/2025 | Corrections Issued | JUAN VALENZUELA |
| Final | 4/3/2025 | OK to Issue CofO | JUAN VALENZUELA |