1749 1/2 S MARVIN AVE 90019
Certificate Information: 1749 1/2 S MARVIN AVE 90019
- Application / Permit
- 20010-10000-03949
- Plan Check / Job No.
- B20LA19783
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE (UNIT C). 3 OF 3
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 3/4/2022 | KEVIN MORALES |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 2/2/2026 | BRENDAN MORELLI |
| Permit Finaled | 2/3/2026 | DEROLD HAUFF |
| CofO Issued | 2/3/2026 | DEROLD HAUFF |
| Permit Finaled | 2/3/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/30/2021 | KURT CORRAL |
| Address approval | Cleared | 10/6/2021 | WALLIE JONG |
| Highway dedication | Cleared | 10/6/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | WALLIE JONG |
| Sewer availability | Cleared | 10/19/2021 | WALLIE JONG |
| Building over 36-ft | Cleared | 10/20/2021 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 12/21/2021 | CHRIS PARK |
| Frnt yard landscape/Water mgmt | Cleared | 1/11/2022 | DANIEL CORONADO |
| Tract Map conditions | Cleared | 1/11/2022 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 1/14/2022 | WALLIE JONG |
Contact Information
| Architect | Bittoni,, Mark Christopher; Lic. No.: C34136 | 434 N GREENCRAIG ROAD LOS ANGELES, CA 90049 |
| Contractor | Goodson Real Estate Co; Lic. No.: 977440-B | 6230 WILSHIRE BLVD #1154 LOS ANGELES, CA 90048 |
| Engineer | Morris,, Kyle Byron; Lic. No.: C72911 | 1401 DOVE ST STE 520 NEWPORT BEACH, CA 92660 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2024 | Partial Inspection | ARTHUR NEGRETE |
| Pre-Inspection | 7/3/2024 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/29/2024 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 7/29/2024 | Partial Approval | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 7/31/2024 | Conditional Approval | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 8/9/2024 | Approved | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 8/9/2024 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/9/2024 | Approved | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 8/12/2024 | Conditional Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 9/3/2024 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 9/9/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 9/19/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 10/4/2024 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 10/4/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 10/8/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 10/23/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 12/20/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Rough | 12/23/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Special/Order Compliance | 12/23/2024 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 12/24/2024 | Partial Approval | NICHOLAS LOPEZ |
| HVAC-Rough | 3/18/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Gas Test | 3/20/2025 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 4/1/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 4/21/2025 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 5/15/2025 | Approved | NICHOLAS LOPEZ |
| Sewer | 5/15/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 5/22/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 6/5/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/10/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Wood Frame | 6/16/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/26/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/26/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 6/26/2025 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 6/26/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/30/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 7/1/2025 | Approved | NICHOLAS LOPEZ |
| Special/Order Compliance | 7/1/2025 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 7/2/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 7/3/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 7/10/2025 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 7/15/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 8/28/2025 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 9/5/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 10/6/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 10/23/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 10/24/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 10/24/2025 | Approved | BRENDAN MORELLI |
| Final | 11/5/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 11/5/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 11/5/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 11/5/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 1/13/2026 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Not Ready | BRENDAN MORELLI |
| Service/Power Release | 1/13/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 1/13/2026 | Corrections Issued | BRENDAN MORELLI |
| Final | 1/26/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Gas Test | 1/26/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Not Ready | BRENDAN MORELLI |
| Service/Power Release | 1/26/2026 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 1/26/2026 | Approved | BRENDAN MORELLI |
| Final | 2/2/2026 | OK to Issue CofO | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | BRENDAN MORELLI |