1522 1/2 S BURNSIDE AVE 90019
Certificate Information: 1522 1/2 S BURNSIDE AVE 90019
- Application / Permit
- 20010-10000-03901
- Plan Check / Job No.
- B20LA19609
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY BLDG, ADU ON TOP OF A 2-CAR GARAGE WITH ATTACHED REC. ROOM
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 3/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/1/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/18/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| Applicant returned to address corrections | 8/18/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 2/6/2024 | MAHNAZ NOURHASHEMI |
| Issued | 3/14/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/9/2023 | TOMMY YIN |
| Address approval | Cleared | 6/28/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 7/2/2023 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/30/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 1/19/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/8/2024 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 12/13/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 12/13/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 12/13/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 12/13/2024 | Approved | ARTHUR NEGRETE |
| Deputy Steel/Welding | 1/16/2025 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/21/2025 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/21/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 3/21/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/21/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Rough | 3/21/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/21/2025 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 3/21/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/27/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Rough | 3/27/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/27/2025 | Partial Inspection | ALEX COLIN |
| Verify Sprinkler Sign Off | 3/27/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 4/2/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/2/2025 | Partial Approval | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/4/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 4/8/2025 | Partial Approval | ARTHUR NEGRETE |
| Shower Pan | 4/8/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 4/10/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 6/12/2025 | Approved | ARTHUR NEGRETE |
| Final | 6/12/2025 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 6/12/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/12/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 6/12/2025 | Approved | ARTHUR NEGRETE |
| Final | 7/22/2025 | Partial Approval | ARTHUR NEGRETE |
| Green Building Final | 7/22/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 7/22/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 1/8/2026 | Corrections Issued | BRENDAN MORELLI |