3009 N AMETHYST ST 90032

Certificate Information: 3009 N AMETHYST ST 90032

Application / Permit
20010-10000-03873
Plan Check / Job No.
B20LA19524
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) TWO-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 9/15/2023
Issuing Office
Valley
Current Status
Intent to Revoke on 6/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/22/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 DANIEL YIP
Corrections Issued 11/30/2020 DANIEL YIP
Quality Review Completed 12/4/2020 ALLEN MANALANSAN
Building Plans Picked Up 12/18/2020 APPLICANT
Applicant returned to address corrections 4/6/2022 DANIEL YIP
Plan Check Approved 8/9/2022 DANIEL YIP
Issued 9/15/2023 APPLICANT
Intent to Revoke 6/5/2026 ALLEN MANALANSAN

Permit Application Clearance Information

Address approval Cleared 12/23/2020 RENZ SORIANO
Trees in Parkway Cleared 1/4/2021 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 1/5/2021 PAMELA TENEZA
Hydrant and Access approval Cleared 1/7/2021 MATTHEW CRAIG
Low Impact Development Cleared 3/22/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/22/2021 RENZ SORIANO
Sewer availability Cleared 4/8/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 12/10/2021 JEANETTE VONG
BHO/Hillside ordinance Cleared 12/10/2021 JEANETTE VONG
BHO/Hillside ordinance Cleared 12/14/2021 JEANETTE VONG
BHO/Hillside ordinance Cleared 12/14/2021 JEANETTE VONG
BHO/Hillside ordinance Cleared 12/14/2021 JEANETTE VONG
Excavation more than 5-ft deep Cleared 8/9/2022 CALOSHA APPROVED
GPI Written Notices Cleared 8/9/2022 DANIEL YIP
Grading Pre-Inspection Cleared 8/9/2022 DANIEL YIP
"D" conditions Cleared 8/25/2022 RUBEN VASQUEZ
"Q" conditions Cleared 8/25/2022 RUBEN VASQUEZ
ZA Case Cleared 8/25/2022 RUBEN VASQUEZ
ZI Cleared 8/25/2022 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/26/2023 Corrections Issued OSVALDO PARAMO
Piling/Pier/Caisson 10/31/2023 Corrections Issued OSVALDO PARAMO
Deputy Reinf. Concrete 11/1/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 11/14/2023 Not Ready for Inspection OSVALDO PARAMO
Piling/Pier/Caisson 11/14/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 2/14/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 2/23/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/7/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/18/2024 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/20/2024 Partial Approval OSVALDO PARAMO
Reinforced Masonry Frame 3/29/2024 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 4/2/2024 Partial Approval OSVALDO PARAMO
Reinforced Masonry Frame 4/2/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 4/15/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 4/16/2024 Partial Approval ALIZAH MAYAGOITIA
Insulation 4/18/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Partial Approval OSVALDO PARAMO
Green Building Rough 4/19/2024 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 4/19/2024 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 12/11/2024 Approved WILLIAM SIERRA
PLUMBING-Rough 12/12/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/19/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 12/24/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/13/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 1/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 1/13/2025 Approved ALIZAH MAYAGOITIA
Wood Frame 2/4/2025 Approved ALIZAH MAYAGOITIA
Insulation 2/7/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/7/2025 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/19/2025 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 3/10/2025 Approved ANTHONY RAMOS
Green Building Rough 3/10/2025 Approved ANTHONY RAMOS
Shower Pan 3/20/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 3/26/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 7/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 7/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/25/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 7/25/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 7/25/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 2/10/2026 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/20/2026 Approved ALIZAH MAYAGOITIA
Final 3/20/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/20/2026 Approved ALIZAH MAYAGOITIA
Green Building Final 3/20/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV No Gas ALIZAH MAYAGOITIA
Smoke Detectors 3/20/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/7/2026 Approved OSVALDO PARAMO
Final 5/11/2026 Conditional Approval OSVALDO PARAMO
PLUMBING-Final 5/12/2026 Approved OSVALDO PARAMO
Special/Order Compliance 6/4/2026 Partial Inspection LILIANA PORTILLO