21322 W OXNARD ST 91367

Certificate Information: 21322 W OXNARD ST 91367

Application / Permit
20010-10000-03853
Plan Check / Job No.
B20LA19427
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Patio Cover
Work Description
1-story 9'x20'8" detached trellis accessory to restaurant use.
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
Permit Finaled on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 MICHAEL LOPEZ
Disabled Access Plans Picked Up 11/5/2020 APPLICANT
Corrections Issued 11/12/2020 MICHAEL LOPEZ
Quality Review Completed 11/21/2020 PRANITA SHAH
Building Plans Picked Up 12/23/2020 APPLICANT
Applicant returned to address corrections 3/16/2021 MICHAEL LOPEZ
Applicant returned to address corrections 4/1/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/18/2021 MICHAEL LOPEZ
Applicant returned to address corrections 7/16/2021 TU HUA
Plan Check Approved 7/28/2021 TU HUA
Issued 8/12/2021 APPLICANT
Permit Finaled 6/2/2022 KENNETH ROBERTS

Permit Application Clearance Information

Miscellaneous Cleared 12/8/2020 RICHARD REASER
Miscellaneous Cleared 12/8/2020 RICHARD REASER
Miscellaneous Cleared 12/8/2020 RICHARD REASER
Miscellaneous Cleared 12/8/2020 RICHARD REASER
DAS Clearance Cleared 2/8/2021 SHINE LIN
Specific Plan Cleared 2/9/2021 KRISTINE JEGALIAN

Contact Information

Architect Valerio,, Niccolo; Lic. No.: C24228 5858 WILSHIRE BLVD # 203      LOS ANGELES, CA 90036
Contractor Padelford A J & Son Inc; Lic. No.: 222840-B P O BOX 185      ARTESIA, CA 907020185
Engineer Momeni,, Moe; Lic. No.: C56774 8772 RAINBOW RIDGE      LAS VEGAS, NV 89117

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2021 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 12/13/2021 Approved CAMERON CHABAN
Footing/Foundation/Slab 2/10/2022 Approved DANIEL VARNUM
Drywall Nailing 3/21/2022 Approved CAMERON CHABAN
Final 3/21/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 3/21/2022 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 3/21/2022 Approved CAMERON CHABAN
Wood Frame 3/21/2022 Approved CAMERON CHABAN
Final 4/6/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV No Gas CAMERON CHABAN
Final 5/18/2022 Partial Inspection CAMERON CHABAN
Final 5/31/2022 Partial Inspection CAMERON CHABAN
Final 6/2/2022 Permit Finaled KENNETH ROBERTS