6351 W CENTURY BLVD 90045
Certificate Information: 6351 W CENTURY BLVD 90045
- Application / Permit
- 20010-10000-03838
- Plan Check / Job No.
- B20LA19343
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Canopy
- Work Description
- TEMPORARY PERMIT FOR NEW CANOPIES AT LAX. TOTAL 28 QTY CANOPIES, INCLUDING (2 QTY) 20 FT X 20FT FOR PEDESTRIAN ACCESS AREA AND (26QTY) 40 FT X 10 FT FOR TAXI, OPOLI, UBER, AND LYFT.
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | GARO TELMI |
| Corrections Issued | 10/28/2020 | GARO TELMI |
| Disabled Access Plans Picked Up | 10/30/2020 | APPLICANT |
| Quality Review Completed | 11/5/2020 | LIPING TENG |
| Building Plans Picked Up | 11/6/2020 | APPLICANT |
| Applicant returned to address corrections | 12/3/2020 | GARO TELMI |
| Plan Check Approved | 1/15/2021 | GARO TELMI |
| Issued | 1/21/2021 | APPLICANT |
| CofO in Progress | 6/23/2021 | TED RIES |
| Permit Finaled | 6/23/2021 | TED RIES |
| CofO Issued | 6/23/2021 | TED RIES |
| Permit Finaled | 6/23/2021 | TED RIES |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/4/2020 | SHINE LIN |
| Project Permit | Cleared | 12/3/2020 | VINITA WASKOW |
| Roof/Waste drainage to street | Cleared | 12/3/2020 | MARYAM AZARBAYJANI |
| Airport buildings | Cleared | 12/11/2020 | ANDREW KO |
| Specific Plan | Cleared | 12/18/2020 | PEDRO AYALA |
| Low Impact Development | Cleared | 1/12/2021 | IDA MEISAMI-FARD |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | MARYAM AZARBAYJANI |
Contact Information
| Contractor | Swinerton Builders; Lic. No.: 92-B | 2001 CLAYTON RD 7TH FLOOR - LEGAL CONCORD, CA 94520 |
| Engineer | Kehl,, Russell Jacob; Lic. No.: S4741 | 13314 JUDAH AVE HAWTHORNE, CA 90250 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/26/2021 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 1/26/2021 | Approved | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV No Gas | TED RIES |
| Smoke Detectors | 1/26/2021 | Approved | TED RIES |
| Verify Sprinkler Sign Off | 1/26/2021 | Approved | TED RIES |
| Wood Frame | 1/26/2021 | Approved | TED RIES |