700 1/2 E 103RD PL 90002
Certificate Information: 700 1/2 E 103RD PL 90002
- Application / Permit
- 20010-10000-03814
- Plan Check / Job No.
- B20LA19286
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1,199 SF ONE STORY ADU ALLOWED PER LA CITY ORDINANCE PER WFPP see comment.
- Permit Issued
- Issued on 8/10/2021
- Issuing Office
- Current Status
- CofO Issued on 1/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2020 | RAHEL BEYENE |
| Corrections Issued | 11/4/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 7/17/2021 | TSE MING HUANG |
| Plan Check Approved | 7/22/2021 | TSE MING HUANG |
| Issued | 8/10/2021 | APPLICANT |
| Building Plans Picked Up | 8/19/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | JOHN KLARIN |
| Permit Finaled | 1/12/2023 | ANSON MAGLASANG |
| CofO Issued | 1/12/2023 | ANSON MAGLASANG |
| Permit Finaled | 1/12/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/10/2021 | RIDWAN HARDY |
| Address approval | Cleared | 3/4/2021 | CELINA MORENO |
| Sewer availability | Cleared | 3/11/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 4/26/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/7/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/3/2021 | KURT CORRAL |
Contact Information
| Contractor | Redstar Construction; Lic. No.: 1027569-B | 16155 SIERRA LAKES PKWAY STE 160-634 FONTANA, CA 92336 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/20/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/27/2021 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 11/5/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/5/2021 | Approved | EUGENE CASSIDY |
| Insulation | 12/7/2021 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 12/16/2021 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/21/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 12/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 12/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 1/6/2022 | Approved | EUGENE CASSIDY |
| Insulation | 1/6/2022 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 1/12/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 4/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | JOHN KLARIN |
| Interior/Exterior Lathing | 5/9/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/16/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/16/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/16/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/16/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 5/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/16/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/20/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/20/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/20/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/26/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/23/2022 | Approved | JOHN KLARIN |
| Pre-Inspection | 8/19/2022 | Approved | JOHN KLARIN |
| Pre-Inspection | 8/25/2022 | Approved | JOHN KLARIN |
| Pre-Inspection | 9/7/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 9/7/2022 | Approved | EUGENE CASSIDY |
| Final | 11/8/2022 | No Access for Inspection | JOHN KLARIN |
| Green Building Final | 11/8/2022 | No Access for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 11/8/2022 | No Access for Inspection | JOHN KLARIN |
| Smoke Detectors | 11/8/2022 | No Access for Inspection | JOHN KLARIN |
| Final | 11/17/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 11/17/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 11/17/2022 | Corrections Issued | JOHN KLARIN |
| Smoke Detectors | 11/17/2022 | Approved | JOHN KLARIN |
| Final | 11/28/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 11/28/2022 | Approved | JOHN KLARIN |
| Service/Power Release | 11/28/2022 | Approved | JOHN KLARIN |
| Final | 12/12/2022 | OK to Issue CofO | JOHN KLARIN |