700 1/2 E 103RD PL 90002

Certificate Information: 700 1/2 E 103RD PL 90002

Application / Permit
20010-10000-03814
Plan Check / Job No.
B20LA19286
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1,199 SF ONE STORY ADU ALLOWED PER LA CITY ORDINANCE PER WFPP see comment.
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
CofO Issued on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/30/2020 RAHEL BEYENE
Corrections Issued 11/4/2020 RAHEL BEYENE
Applicant returned to address corrections 7/17/2021 TSE MING HUANG
Plan Check Approved 7/22/2021 TSE MING HUANG
Issued 8/10/2021 APPLICANT
Building Plans Picked Up 8/19/2021 APPLICANT
CofO in Progress 12/13/2022 JOHN KLARIN
Permit Finaled 1/12/2023 ANSON MAGLASANG
CofO Issued 1/12/2023 ANSON MAGLASANG
Permit Finaled 1/12/2023 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 2/10/2021 RIDWAN HARDY
Address approval Cleared 3/4/2021 CELINA MORENO
Sewer availability Cleared 3/11/2021 CELINA MORENO
Low Impact Development Cleared 4/26/2021 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 5/7/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 5/7/2021 CELINA MORENO
Hydrant and Access approval Cleared 6/3/2021 KURT CORRAL

Contact Information

Contractor Redstar Construction; Lic. No.: 1027569-B 16155 SIERRA LAKES PKWAY   STE 160-634    FONTANA, CA 92336

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/20/2021 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/27/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 10/27/2021 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/5/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 11/5/2021 Approved EUGENE CASSIDY
Insulation 12/7/2021 Corrections Issued EUGENE CASSIDY
Insulation 12/16/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 12/21/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 12/21/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 12/21/2021 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/6/2022 Approved EUGENE CASSIDY
Insulation 1/6/2022 Corrections Issued EUGENE CASSIDY
Insulation 1/12/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 4/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 4/1/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 5/9/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/16/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/16/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 5/16/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 5/16/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 5/16/2022 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 5/16/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 5/16/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/20/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/20/2022 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 5/20/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 5/20/2022 Approved ALIZAH MAYAGOITIA
Insulation 5/26/2022 Corrections Issued ALIZAH MAYAGOITIA
Drywall Nailing 6/23/2022 Approved JOHN KLARIN
Pre-Inspection 8/19/2022 Approved JOHN KLARIN
Pre-Inspection 8/25/2022 Approved JOHN KLARIN
Pre-Inspection 9/7/2022 Approved EUGENE CASSIDY
Shower Pan 9/7/2022 Approved EUGENE CASSIDY
Final 11/8/2022 No Access for Inspection JOHN KLARIN
Green Building Final 11/8/2022 No Access for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready JOHN KLARIN
Service/Power Release 11/8/2022 No Access for Inspection JOHN KLARIN
Smoke Detectors 11/8/2022 No Access for Inspection JOHN KLARIN
Final 11/17/2022 Corrections Issued JOHN KLARIN
Green Building Final 11/17/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/17/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 11/17/2022 Corrections Issued JOHN KLARIN
Smoke Detectors 11/17/2022 Approved JOHN KLARIN
Final 11/28/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 11/28/2022 Approved JOHN KLARIN
Service/Power Release 11/28/2022 Approved JOHN KLARIN
Final 12/12/2022 OK to Issue CofO JOHN KLARIN