4058 S MCKINLEY AVE 90011
Certificate Information: 4058 S MCKINLEY AVE 90011
- Application / Permit
- 20010-10000-03744
- Plan Check / Job No.
- B20LA18992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD W/ ATTACHED 1 CAR GARAGE (FRONT) 1 OF 2
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- Issued on 3/25/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | MONICA RAMIREZ |
| Corrections Issued | 10/26/2020 | MONICA RAMIREZ |
| Quality Review Completed | 11/13/2020 | TU HUA |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| Applicant returned to address corrections | 1/21/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/22/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/8/2021 | MONICA RAMIREZ |
| Plan Check Approved | 2/9/2021 | MONICA RAMIREZ |
| No Progress | 3/2/2021 | MONICA RAMIREZ |
| Plan Check Approved | 3/25/2021 | MONICA RAMIREZ |
| Plan Check Approved | 3/25/2021 | MONICA RAMIREZ |
| Issued | 3/25/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2020 | THOMAS LANG |
| Sewer availability | Cleared | 11/10/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 12/9/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/22/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/28/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | 8a General Construction; Lic. No.: 1020625-B | 11660 EL GRANADA AVE LYNWOOD, CA 90262 |
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/5/2021 | Partial Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 4/15/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/19/2022 | No Access for Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 10/19/2022 | No Access for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 11/29/2022 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 11/29/2022 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/17/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 3/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 3/17/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 3/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/5/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 7/5/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/27/2023 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/11/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/18/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/22/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/2/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/20/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/4/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |