1008-1008 1/2 E 23RD ST 90011

Certificate Information: 1008-1008 1/2 E 23RD ST 90011

Application / Permit
20010-10000-03740
Plan Check / Job No.
B20LA18977
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX AT REAR OF LOT
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 6/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 MAHNAZ NOURHASHEMI
Corrections Issued 11/21/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 12/4/2020 TIEN JEN WANG
Building Plans Picked Up 12/10/2020 APPLICANT
Plan Check Approved 4/21/2021 MAHNAZ NOURHASHEMI
Issued 4/21/2021 APPLICANT
CofO in Progress 5/23/2022 JOAQUIN GREENOUGH
Permit Finaled 6/16/2022 DEROLD HAUFF
CofO Issued 6/16/2022 DEROLD HAUFF
Permit Finaled 6/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/1/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 3/9/2021 JEANIE LAM
Sewer availability Cleared 3/9/2021 JEANIE LAM
"Q" conditions Cleared 3/17/2021 MAXFIELD VERMY
Hydrant and Access approval Cleared 3/22/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/9/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/12/2021 JEANIE LAM

Contact Information

Contractor New World Construction; Lic. No.: 864461-B 838 E 93RD STREET      LOS ANGELES, CA 90002
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/1/2021 Partial Approval ROBERT MCDOWELL
Underground Mechanical 6/1/2021 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 6/4/2021 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 6/4/2021 Approved ROBERT MCDOWELL
METHANE-Barrier 6/4/2021 Approved ROBERT MCDOWELL
METHANE-Subgrade 6/4/2021 Approved ROBERT MCDOWELL
Deputy Reinf. Concrete 6/9/2021 Approved HORACE FULTZ
Deputy Wood Construction 8/19/2021 Approved HORACE FULTZ
PLUMBING-Rough 9/7/2021 Corrections Issued ALAN MORELOS
ELECTRICAL-Rough 9/8/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/8/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/9/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 9/9/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 9/9/2021 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 9/9/2021 Approved JOAQUIN GREENOUGH
Wood Frame 9/10/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 9/16/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 9/16/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/16/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 9/21/2021 Approved JOAQUIN GREENOUGH
Special/Order Compliance 9/24/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 9/29/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/29/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 2/14/2022 Approved JOAQUIN GREENOUGH
Final 2/14/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/14/2022 Approved JOAQUIN GREENOUGH
Gas Test 2/14/2022 Approved JOAQUIN GREENOUGH
Green Building Final 2/14/2022 Approved JOAQUIN GREENOUGH
HVAC-Final 2/14/2022 Approved JOAQUIN GREENOUGH
METHANE-Barrier 2/14/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Final 2/14/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 2/14/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 2/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 2/14/2022 Approved JOAQUIN GREENOUGH
Pre-Inspection 2/18/2022 Not Ready for Inspection JUSTIN CURTIS
Final 5/11/2022 Corrections Issued JOAQUIN GREENOUGH
Service/Power Release 5/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 5/18/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 5/18/2022 Approved JOAQUIN GREENOUGH