1979 W 104TH ST 90047
Certificate Information: 1979 W 104TH ST 90047
- Application / Permit
- 20010-10000-03726
- Plan Check / Job No.
- B20LA18917
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 7/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 10/24/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/21/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 12/6/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 12/21/2020 | ARSALAN SHABESTARI |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 7/12/2021 | FREDDIE RIVERA |
| Permit Finaled | 7/27/2021 | DEROLD HAUFF |
| CofO Issued | 7/27/2021 | DEROLD HAUFF |
| Permit Finaled | 7/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 11/9/2020 | RENZ SORIANO |
| Construction near power lines | Cleared | 11/23/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | 8757 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2021 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 3/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Rough | 3/26/2021 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/7/2021 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 4/7/2021 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/7/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/14/2021 | Approved | FREDDIE RIVERA |
| Sewer | 4/14/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 4/14/2021 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 5/3/2021 | Corrections Issued | FREDDIE RIVERA |
| Final | 6/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/8/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/28/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/28/2021 | Approved | FREDDIE RIVERA |
| Green Building Final | 6/28/2021 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 6/28/2021 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 6/28/2021 | Approved | FREDDIE RIVERA |
| Service/Power Release | 6/28/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/28/2021 | Approved | FREDDIE RIVERA |