11001 S BROADWAY 1-55 90061

Certificate Information: 11001 S BROADWAY 1-55 90061

Application / Permit
20010-10000-03685
Plan Check / Job No.
B20LA18788
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5 STORY 55 UNIT 100% AFFORDABLE HOUSING APARTMENT TO INCLUDE 4 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA SUPPORTIVE OFFICE/ COMMUNITY SPACE, DENSITY BONUS PROJECT WITH ADDITIONAL INCENTIVES, PUBLICALLY FUNDED.
Permit Issued
Issued on 6/24/2021
Issuing Office
Metro
Current Status
CofO Issued on 9/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 VU NGUYEN
Corrections Issued 10/29/2020 VU NGUYEN
Quality Review Completed 10/29/2020 RODOLFO ARIAS
Building Plans Picked Up 11/5/2020 APPLICANT
Disabled Access Plans Picked Up 11/13/2020 APPLICANT
Applicant returned to address corrections 12/22/2020 VU NGUYEN
Applicant returned to address corrections 1/5/2021 VU NGUYEN
Applicant returned to address corrections 4/14/2021 VU NGUYEN
Green Plans Picked Up 6/14/2021 APPLICANT
Applicant returned to address corrections 6/22/2021 VU NGUYEN
Plan Check Approved 6/22/2021 VU NGUYEN
Plan Check Approved 6/24/2021 VU NGUYEN
Issued 6/24/2021 APPLICANT
TCO Issued (Expire Date: 11-14-2023) 5/18/2023 TED RIES
CofO in Progress 9/20/2023 JAMES POWERS
CofO Issued 9/20/2023 ERNESTO CORRAL
Permit Finaled 9/20/2023 ERNESTO CORRAL

Permit Application Clearance Information

Encroachment in public way Cleared 11/9/2020 ELENA LOPEZ
Green Code Cleared 12/15/2020 AARON COSTA
Address approval Cleared 12/29/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/4/2021 JEANIE LAM
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Fire Marshal Fire Life Safety Cleared 1/20/2021 ANDREW KO
Sewer availability Cleared 3/9/2021 JEANIE LAM
Highway dedication Cleared 3/23/2021 JEANIE LAM
Low Impact Development Cleared 4/9/2021 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 4/12/2021 JEANIE LAM
"Q" conditions Cleared 4/21/2021 JASON CHAN
ZA Case Cleared 4/21/2021 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 4/23/2021 JASON CHAN
Historic Resource Verification Cleared 4/23/2021 DAVID URITA
Opn space landscape/Water mgmt Cleared 4/23/2021 JASON CHAN
Redevelopment Project Area Cleared 4/23/2021 DAVID URITA
Trees in Parkway Cleared 4/29/2021 JOHN KIM
Building over 36-ft Cleared 5/20/2021 CALOSHA APPROVED
Public Housing Cleared 5/26/2021 JORGE ALCANTAR
Permit Cleared 6/1/2021 CECILIO NAVARRO
Density Bonus 12.22.A.25 Cleared 6/8/2021 DORIS KWOK
Density Bonus 12.22.A.31 Cleared 6/8/2021 DORIS KWOK
Construction near power lines Cleared 6/12/2021 RIDWAN HARDY
DAS Clearance Cleared 6/18/2021 VU NGUYEN
Miscellaneous Cleared 6/22/2021 JASON CHAN

Contact Information

Architect Greer,, Thomas Edward; Lic. No.: C25207 27741 MOTHERLODE COURT      LAGUNA NIGUEL, CA 92677
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer , ; Lic. No.: S5432       ,
Engineer Agopian,, Jack; Lic. No.: C75615 635 W BROADWAY      GLENDALE, CA 91204
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042

Inspector Information

JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/12/2021 Not Ready for Inspection JAMES POWERS
Pre-Inspection 8/12/2021 Approved JAMES POWERS
Deputy Reinf. Concrete 8/31/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/31/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 9/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2021 Partial Approval JAMES POWERS
Green Building Rough 9/21/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/21/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/21/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/22/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/1/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 10/4/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/17/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 11/18/2021 Conditional Approval TED RIES
Green Building Rough 11/18/2021 Partial Approval TED RIES
Reinforced Masonry Frame 11/18/2021 Partial Approval TED RIES
Verify Sprinkler Sign Off 11/18/2021 Partial Approval TED RIES
Deputy Reinf. Masonry 11/19/2021 Conditional Approval TED RIES
Deputy Drilled-In Anchors 11/22/2021 Approved TED RIES
Deputy Reinf. Concrete 11/23/2021 Conditional Approval TED RIES
Footing/Foundation/Slab 11/23/2021 Partial Approval TED RIES
Deputy Reinf. Concrete 11/24/2021 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/6/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/6/2021 Partial Approval JAMES POWERS
Green Building Rough 12/16/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/16/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/16/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 12/22/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/27/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/28/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/29/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/30/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/4/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/5/2022 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/6/2022 Partial Approval JAMES POWERS
Green Building Rough 1/6/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/6/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/6/2022 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 1/7/2022 Approved TED RIES
Deputy Pre-Stress Concrete 1/10/2022 Partial Approval JAMES POWERS
Structural Steel Frame 1/10/2022 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 1/13/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/2/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/2/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/3/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval TED RIES
Deputy Wood Construction 4/8/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 4/11/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 4/14/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval BRUCE CAMPBELL
Drywall Nailing 5/5/2022 Partial Approval JAMES POWERS
Insulation 5/19/2022 Partial Approval JAMES POWERS
Insulation 5/23/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/6/2022 Partial Approval JAMES POWERS
Insulation 6/29/2022 Partial Approval JAMES POWERS
Insulation 7/7/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/4/2022 Partial Approval JAMES POWERS
Insulation 8/9/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/17/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/25/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 9/1/2022 Partial Approval JAMES POWERS
Drywall Nailing 11/10/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/2/2023 Not Ready for Inspection JAMES POWERS
Final 5/10/2023 Partial Inspection JAMES POWERS
Footing/Foundation/Slab 5/10/2023 Approved JAMES POWERS
Green Building Final 5/10/2023 Approved JAMES POWERS
Green Building Rough 5/10/2023 Approved JAMES POWERS
Reinforced Concrete Frame 5/10/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/10/2023 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 5/10/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 5/10/2023 Not Ready for Inspection JAMES POWERS
Final 5/18/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/18/2023 Approved JAMES POWERS
Reinforced Masonry Frame 5/18/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 5/18/2023 Approved JAMES POWERS
Final 9/18/2023 Not Ready for Inspection JAMES POWERS
Final 9/20/2023 OK to Issue CofO JAMES POWERS