12500 W SHERMAN WAY 91605

Certificate Information: 12500 W SHERMAN WAY 91605

Application / Permit
20010-10000-03679
Plan Check / Job No.
B20LA18750
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Gasoline Station
Work Description
NEW FUEL CANOPY( GAS STATION ) WITH UNDERGROUND STORAGE TANKS
Permit Issued
Issued on 9/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 GARO TELMI
Green Plans Picked Up 12/9/2020 APPLICANT
Disabled Access Plans Picked Up 12/29/2020 APPLICANT
Corrections Issued 12/30/2020 GARO TELMI
Quality Review Completed 1/12/2021 WING SUEN
Building Plans Picked Up 1/19/2021 APPLICANT
Applicant returned to address corrections 8/13/2021 GARO TELMI
Applicant returned to address corrections 8/26/2021 GARO TELMI
Applicant returned to address corrections 9/2/2021 GARO TELMI
Applicant returned to address corrections 10/5/2021 GARO TELMI
Applicant returned to address corrections 11/1/2021 GARO TELMI
Applicant returned to address corrections 7/11/2022 GARO TELMI
Applicant returned to address corrections 7/15/2022 GARO TELMI
Plan Check Approved 9/19/2022 GARO TELMI
Issued 9/29/2022 APPLICANT
TCO Issued (Expire Date: 04-27-2025) 10/29/2024 JEFFREY DURAN
CofO in Progress 11/18/2024 JOHN KITCKO
Permit Finaled 11/19/2024 RICKEY JACKSON
CofO Issued 11/19/2024 RICKEY JACKSON
Permit Finaled 11/19/2024 RICKEY JACKSON

Permit Application Clearance Information

Automotive Use Cleared 8/16/2021 TERRI OSBORNE
Automotive Use Cleared 8/16/2021 TERRI OSBORNE
Comm Cor/Mini-Mall Cleared 8/16/2021 TERRI OSBORNE
Comm Cor/Mini-Mall Cleared 8/16/2021 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 9/20/2021 GABRIEL ROBLES
Address approval Cleared 9/22/2021 GABRIEL ROBLES
Driveway location Cleared 9/22/2021 DURRE SHAMSI
Internal circulation Cleared 9/22/2021 DURRE SHAMSI
Hydrant and Access approval Cleared 9/28/2021 KURT CORRAL
Driveway location Cleared 10/13/2021 DURRE SHAMSI
Trees in Parkway Cleared 10/28/2021 ADALBERTO VERA
Highway dedication Cleared 11/18/2021 CARLOS AGUILERA
Permit Cleared 11/18/2021 CARLOS AGUILERA
Automotive Use Cleared 12/7/2021 NOAH MCCOY
Comm Cor/Mini-Mall Cleared 12/7/2021 NOAH MCCOY
Frnt yard landscape/Water mgmt Cleared 12/7/2021 NOAH MCCOY
Prkng lot landscape/Water mgmt Cleared 12/7/2021 NOAH MCCOY
ZA Case Cleared 12/7/2021 NOAH MCCOY
Green Code Cleared 12/14/2021 GARO TELMI
Roof/Waste drainage to street Cleared 1/28/2022 LEE GUILBEAUX
Low Impact Development Cleared 1/31/2022 AMMAR ELTAWIL
Sewer availability Cleared 2/1/2022 CARLOS AGUILERA
DAS Clearance Cleared 2/7/2022 GARO TELMI
Work Adjacent to Public Way Cleared 6/17/2022 LEE GUILBEAUX
Gasoline station Cleared 9/19/2022 SCAQMD APPROVED
Solvents/fuels Cleared 9/19/2022 SCAQMD APPROVED

Contact Information

Contractor R D Builders Inc; Lic. No.: 445832-B 4583 E EISENHOWER CIRCLE      ANAHEIM, CA 92807
Engineer Fiedler,, Patrick O'Neill; Lic. No.: C38123 299 N EUCLID AVE SUITE 550      PASADENA, CA 91101
Engineer Haran,, Charles Arthur; Lic. No.: C57315 8687 N BACKER      FRESNO, CA 93720
Engineer Peyton,, David E; Lic. No.: S3288 5722 E THE TOLEDO      LONG BEACH, CA 90803
Engineer Queyrel,, David Calvin; Lic. No.: L7703 2153 TRAYNOR AVE      PLACENTIA, CA 92870

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/16/2023 Not Ready for Inspection JOHN KITCKO
METHANE-Barrier 2/16/2023 Not Ready for Inspection JOHN KITCKO
METHANE-Subgrade 2/16/2023 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 2/17/2023 Conditional Approval JOHN KITCKO
METHANE-Barrier 2/17/2023 Not Ready for Inspection JOHN KITCKO
METHANE-Subgrade 2/17/2023 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 5/31/2023 Partial Approval JOHN KITCKO
METHANE-Barrier 5/31/2023 Partial Inspection JOHN KITCKO
METHANE-Subgrade 5/31/2023 Partial Approval JOHN KITCKO
Special/Order Compliance 8/13/2024 Approved JOHN KITCKO
Final 10/28/2024 OK for TCO JOHN KITCKO
Footing/Foundation/Slab 10/28/2024 Approved JOHN KITCKO
Green Building Final 10/28/2024 Approved JOHN KITCKO
Green Building Rough 10/28/2024 Approved JOHN KITCKO
METHANE-Barrier 10/28/2024 Approved JOHN KITCKO
METHANE-Final 10/28/2024 Approved JOHN KITCKO
METHANE-Rough 10/28/2024 Approved JOHN KITCKO
METHANE-Subgrade 10/28/2024 Approved JOHN KITCKO
Reinforced Masonry Frame 10/28/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 10/28/2024 Approved JOHN KITCKO
Verify Sprinkler Sign Off 10/28/2024 Approved JOHN KITCKO
Final 11/18/2024 OK to Issue CofO JOHN KITCKO