432 N MCDONALD AVE 90744
Certificate Information: 432 N MCDONALD AVE 90744
- Application / Permit
- 20010-10000-03676
- Plan Check / Job No.
- B20LA18728
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | STARR CHEN |
| Corrections Issued | 12/14/2020 | STARR CHEN |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
| Quality Review Completed | 6/18/2021 | RODOLFO ARIAS |
| Plan Check Approved | 6/18/2021 | STARR CHEN |
| Issued | 6/21/2021 | APPLICANT |
| CofO in Progress | 2/17/2023 | EUGENE CASSIDY |
| Permit Finaled | 2/27/2023 | ANSON MAGLASANG |
| CofO Issued | 2/27/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/27/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 2/3/2021 | RUBEN VASQUEZ |
| Address approval | Cleared | 2/22/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | CHINH DINH |
| Sewer availability | Cleared | 2/23/2021 | CHINH DINH |
| Abandoned oil well | Cleared | 3/2/2021 | JEREMY CARTER |
| Hydrant and Access approval | Cleared | 3/2/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 5/2/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/5/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2021 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 10/27/2021 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Barrier | 10/27/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 10/27/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/12/2023 | Approved | EUGENE CASSIDY |
| Final | 1/12/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/12/2023 | Approved | EUGENE CASSIDY |
| Green Building Final | 1/12/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 1/12/2023 | Approved | EUGENE CASSIDY |
| METHANE-Final | 1/12/2023 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 1/12/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 1/12/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 1/12/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/12/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 1/30/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/30/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 1/30/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/7/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/7/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 2/7/2023 | Not Required | EUGENE CASSIDY |
| Final | 2/13/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/17/2023 | Approved | EUGENE CASSIDY |
| Final | 2/17/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/17/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/17/2023 | Approved | EUGENE CASSIDY |