131-133 W 110TH ST 90061

Certificate Information: 131-133 W 110TH ST 90061

Application / Permit
20010-10000-03675
Plan Check / Job No.
B20LA18722
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 MAHNAZ NOURHASHEMI
Corrections Issued 11/6/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 11/18/2020 TIEN JEN WANG
Building Plans Picked Up 11/19/2020 APPLICANT
Plan Check Approved 2/2/2021 MAHNAZ NOURHASHEMI
Issued 2/3/2021 APPLICANT
CofO in Progress 8/6/2021 ANSON MAGLASANG
Permit Finaled 8/10/2021 DEROLD HAUFF
CofO Issued 8/10/2021 DEROLD HAUFF
Permit Finaled 8/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/24/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/24/2020 JEANIE LAM
Permit Cleared 11/24/2020 JEANIE LAM
Sewer availability Cleared 11/24/2020 JEANIE LAM
Hydrant and Access approval Cleared 12/23/2020 JEREMY CARTER
Low Impact Development Cleared 12/29/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/12/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2021 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 2/25/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/5/2021 Partial Approval EUGENE CASSIDY
Sewer 3/5/2021 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 3/5/2021 Approved EUGENE CASSIDY
Wood Frame 3/5/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Partial Approval EUGENE CASSIDY
Insulation 3/8/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 4/21/2021 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval EUGENE CASSIDY
Special/Order Compliance 4/30/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 5/6/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/6/2021 Approved EUGENE CASSIDY
Green Building Rough 5/6/2021 Approved EUGENE CASSIDY
HVAC-Rough 5/6/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 5/6/2021 Approved EUGENE CASSIDY
Sewer 5/6/2021 Approved EUGENE CASSIDY
Underground Mechanical 5/6/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 5/6/2021 Approved EUGENE CASSIDY
Insulation 5/13/2021 Approved EUGENE CASSIDY
Drywall Nailing 5/25/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/25/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/23/2021 Approved EUGENE CASSIDY
Final 7/23/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 7/23/2021 Approved EUGENE CASSIDY
HVAC-Final 7/23/2021 Approved EUGENE CASSIDY
PLUMBING-Final 7/23/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 7/23/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 7/23/2021 Approved EUGENE CASSIDY
Final 8/6/2021 OK to Issue CofO ANSON MAGLASANG
Service/Power Release 8/6/2021 Approved ANSON MAGLASANG