131-133 W 110TH ST 90061
Certificate Information: 131-133 W 110TH ST 90061
- Application / Permit
- 20010-10000-03675
- Plan Check / Job No.
- B20LA18722
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/6/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/18/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Plan Check Approved | 2/2/2021 | MAHNAZ NOURHASHEMI |
| Issued | 2/3/2021 | APPLICANT |
| CofO in Progress | 8/6/2021 | ANSON MAGLASANG |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
| CofO Issued | 8/10/2021 | DEROLD HAUFF |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | JEANIE LAM |
| Permit | Cleared | 11/24/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/24/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 12/23/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 12/29/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/12/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2021 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 2/25/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 3/5/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 3/5/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 3/5/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 3/5/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 3/8/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 4/21/2021 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | EUGENE CASSIDY |
| Special/Order Compliance | 4/30/2021 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/6/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/6/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/6/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/6/2021 | Approved | EUGENE CASSIDY |
| Sewer | 5/6/2021 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 5/6/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/6/2021 | Approved | EUGENE CASSIDY |
| Insulation | 5/13/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/25/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/25/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/23/2021 | Approved | EUGENE CASSIDY |
| Final | 7/23/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/23/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 7/23/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 7/23/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 7/23/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 7/23/2021 | Approved | EUGENE CASSIDY |
| Final | 8/6/2021 | OK to Issue CofO | ANSON MAGLASANG |
| Service/Power Release | 8/6/2021 | Approved | ANSON MAGLASANG |