4004 E VERDANT ST 90039
Certificate Information: 4004 E VERDANT ST 90039
- Application / Permit
- 20010-10000-03674
- Plan Check / Job No.
- B20LA18720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- (N) ONE STORY OFFICE STRUCTURE (ACCESSORY TO MAIN USE ON SITE) WITHIN (E) SHADE STRUCTURE.
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- CofO Issued on 7/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | JOE VO |
| Corrections Issued | 11/8/2020 | JOE VO |
| Disabled Access Plans Picked Up | 11/16/2020 | APPLICANT |
| Quality Review Completed | 11/20/2020 | MINYE PAK |
| Applicant returned to address corrections | 3/9/2021 | JOE VO |
| Green Plans Picked Up | 9/2/2021 | APPLICANT |
| Plan Check Approved | 3/23/2022 | JOE VO |
| Issued | 3/31/2022 | APPLICANT |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| CofO in Progress | 7/10/2023 | DAVID BURKHEAD |
| CofO Issued | 7/11/2023 | ERNESTO CORRAL |
| Permit Finaled | 7/11/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Permit | Cleared | 1/14/2021 | WALLIE JONG |
| ZA Case | Cleared | 1/25/2021 | ANNA VIDAL |
| ZA Case | Cleared | 1/25/2021 | ANNA VIDAL |
| Private street | Cleared | 2/3/2021 | ANNA VIDAL |
| ZI | Cleared | 2/3/2021 | ANNA VIDAL |
| ZI | Cleared | 2/3/2021 | ANNA VIDAL |
| Miscellaneous | Cleared | 2/4/2021 | ANNA VIDAL |
| ZA Case | Cleared | 2/4/2021 | ANNA VIDAL |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/8/2021 | JEREMY CARTER |
| Address approval | Cleared | 7/14/2021 | WALLIE JONG |
| Green Code | Cleared | 8/10/2021 | JOE VO |
| DAS Clearance | Cleared | 8/12/2021 | JOE VO |
| Sewer availability | Cleared | 3/3/2022 | WALLIE JONG |
Contact Information
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/20/2022 | Corrections Issued | DAVID BURKHEAD |
| Special/Order Compliance | 4/22/2022 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 5/10/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/19/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Approved | DAVID BURKHEAD |
| Deputy Wood Construction | 8/16/2022 | Conditional Approval | DAVID BURKHEAD |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 8/16/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 8/16/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Rough | 11/4/2022 | Approved | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 11/4/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 11/4/2022 | Partial Inspection | DAVID BURKHEAD |
| Insulation | 11/15/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Drywall Nailing | 1/4/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Insulation | 1/4/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 1/6/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 1/6/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Final | 1/6/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Not Ready | DAVID BURKHEAD |
| Smoke Detectors | 1/6/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 1/6/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 1/6/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Drywall Nailing | 1/23/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Insulation | 1/23/2023 | Approved | DAVID BURKHEAD |
| Drywall Nailing | 2/1/2023 | Approved | GREGORY POMISH |
| Final | 2/21/2023 | Partial Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 2/21/2023 | Approved | DAVID BURKHEAD |
| Green Building Final | 2/21/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV No Gas | DAVID BURKHEAD |
| Smoke Detectors | 2/21/2023 | Approved | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 2/21/2023 | Approved | DAVID BURKHEAD |
| Wood Frame | 2/21/2023 | Approved | DAVID BURKHEAD |
| Green Building Final | 3/15/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 3/17/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Final | 3/17/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 4/10/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Final | 4/10/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 4/26/2023 | Partial Inspection | DAVID BURKHEAD |
| Green Building Final | 4/26/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 5/11/2023 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Final | 5/11/2023 | Partial Inspection | EDWIN GREGORYONA |
| Final | 7/6/2023 | OK to Issue CofO | DAVID BURKHEAD |
| Green Building Final | 7/6/2023 | Approved | DAVID BURKHEAD |