1321 1/2 N MALTMAN AVE 90026

Certificate Information: 1321 1/2 N MALTMAN AVE 90026

Application / Permit
20010-10000-03673
Plan Check / Job No.
B20LA18700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2-STORY ACCESSORY DWELLING UNIT PER ORDINANCE. SCOPE WILL ALSO INCLUDE AN ATTACHED 322 SQ. FT. DECK COVERED WITH A TRELLIS.
Permit Issued
Issued on 4/18/2021
Issuing Office
Current Status
CofO Issued on 10/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 MICHAEL LOPEZ
Corrections Issued 11/12/2020 MICHAEL LOPEZ
Quality Review Completed 11/26/2020 PRANITA SHAH
Building Plans Picked Up 11/30/2020 APPLICANT
Applicant returned to address corrections 12/23/2020 MICHAEL LOPEZ
Applicant returned to address corrections 1/31/2021 MICHAEL LOPEZ
Applicant returned to address corrections 3/5/2021 MICHAEL LOPEZ
Plan Check Approved 4/7/2021 MICHAEL LOPEZ
Issued 4/18/2021 APPLICANT
CofO in Progress 10/26/2023 RYAN SALAZAR
Permit Finaled 10/30/2023 DEROLD HAUFF
CofO Issued 10/30/2023 DEROLD HAUFF
Permit Finaled 10/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/24/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/30/2020 WALLIE JONG
Sewer availability Cleared 12/17/2020 WALLIE JONG
Hydrant and Access approval Cleared 1/11/2021 JEREMY CARTER
Grading Pre-Inspection Cleared 3/4/2021 ROBERT HUGHES
Low Impact Development Cleared 3/8/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 3/8/2021 ROSA SILVA
GPI Written Notices Cleared 4/7/2021 ALEXANDER HELFER

Contact Information

Contractor Michael N Soumekh; Lic. No.: 773770-B 1140 SOUTH ALFRED STREET      LOS ANGELES, CA 90035
Engineer O'Brien,, Kathleen Anne; Lic. No.: C49498 1058 PACIFIC AVE      SIMI VALLEY, CA 93065

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2021 Approved ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 5/11/2021 Approved ROBERT VORHIS
Footing/Foundation/Slab 6/4/2021 Approved ROBERT VORHIS
PLUMBING-Rough 6/4/2021 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Partial Approval ROBERT VORHIS
Special/Order Compliance 9/23/2021 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 10/18/2021 Approved ROBERT VORHIS
HVAC-Rough 10/18/2021 Approved ROBERT VORHIS
PLUMBING-Rough 10/18/2021 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Approved ROBERT VORHIS
Green Building Rough 11/5/2021 Not Ready for Inspection ROBERT VORHIS
Verify Sprinkler Sign Off 11/5/2021 Corrections Issued ROBERT VORHIS
BUILDING-Rough-Frame 11/24/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 11/24/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 11/24/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 11/24/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/28/2021 No Access for Inspection THOMAS LOGRASSO
Drywall Nailing 12/30/2021 Approved AMY COLIN
Shower Pan 12/30/2021 Not Ready for Inspection AMY COLIN
Interior/Exterior Lathing 3/14/2022 Approved FREDDIE RIVERA
Shower Pan 3/14/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/9/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 6/9/2022 Approved FREDDIE RIVERA
Final 6/9/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 6/9/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 6/9/2022 Approved FREDDIE RIVERA
HVAC-Final 6/9/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Final 6/9/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 6/9/2022 Partial Inspection FREDDIE RIVERA
Smoke Detectors 6/9/2022 Approved FREDDIE RIVERA
Final 11/8/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 11/8/2022 Approved FREDDIE RIVERA
Service/Power Release 11/8/2022 Partial Inspection FREDDIE RIVERA
Final 11/18/2022 Partial Approval RYAN SALAZAR
HVAC-Final 11/18/2022 Approved RYAN SALAZAR
PLUMBING-Final 11/18/2022 Approved RYAN SALAZAR
Service/Power Release 11/18/2022 Approved RYAN SALAZAR
Final 11/22/2022 Partial Approval RYAN SALAZAR
Final 10/26/2023 OK to Issue CofO RYAN SALAZAR