319-319 1/2 E 105TH ST 90003
Certificate Information: 319-319 1/2 E 105TH ST 90003
- Application / Permit
- 20010-10000-03671
- Plan Check / Job No.
- B20LA18686
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 90'-6"X25' 2-STORY DUPLEX WITH FRONT ATTACHED 1-CAR GARAGE AND BACK ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 11/20/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 12/1/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 12/4/2020 | APPLICANT |
| Applicant returned to address corrections | 3/1/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 3/4/2021 | CHUNG-WEN CHUANG |
| Issued | 3/19/2021 | APPLICANT |
| CofO in Progress | 8/18/2021 | EUGENE CASSIDY |
| CofO Issued | 9/2/2021 | DEROLD HAUFF |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | RENZ SORIANO |
| Permit | Cleared | 12/14/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 12/14/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 12/28/2020 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/27/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/28/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 4/26/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/27/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/14/2021 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/14/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/14/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/14/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/14/2021 | Approved | EUGENE CASSIDY |
| Sewer | 6/14/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/14/2021 | Approved | EUGENE CASSIDY |
| Insulation | 6/15/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/22/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 6/22/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/10/2021 | Approved | EUGENE CASSIDY |
| Final | 8/10/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/10/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 8/10/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/10/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 8/10/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 8/10/2021 | Approved | EUGENE CASSIDY |
| Final | 8/17/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 8/17/2021 | Approved | EUGENE CASSIDY |