739-739 1/2 E 109TH ST 90059
Certificate Information: 739-739 1/2 E 109TH ST 90059
- Application / Permit
- 20010-10000-03670
- Plan Check / Job No.
- B20LA18681
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE PER ENGINEER DESIGN, NFPA 13D THRUOUT
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | AUNG SOE |
| Corrections Issued | 11/9/2020 | AUNG SOE |
| Quality Review Completed | 11/12/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 11/16/2020 | APPLICANT |
| Plan Check Approved | 4/23/2021 | AUNG SOE |
| Plan Check Approved | 7/9/2021 | AUNG SOE |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 12/23/2021 | JOHN KLARIN |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
| CofO Issued | 1/3/2022 | DEROLD HAUFF |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/18/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 11/23/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/25/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/25/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 8/27/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 8/30/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/5/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/5/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/5/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/5/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/5/2021 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/5/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/5/2021 | Approved | EUGENE CASSIDY |
| Insulation | 10/6/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/14/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/14/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/15/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 11/23/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/9/2021 | Approved | JOHN KLARIN |
| Final | 12/9/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 12/9/2021 | Approved | JOHN KLARIN |
| HVAC-Final | 12/9/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 12/9/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2021 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 12/9/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 12/9/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 12/9/2021 | Approved | JOHN KLARIN |
| Final | 12/22/2021 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 12/22/2021 | Approved | JOHN KLARIN |