247-247 1/2 E 119TH ST 90061

Certificate Information: 247-247 1/2 E 119TH ST 90061

Application / Permit
20010-10000-03669
Plan Check / Job No.
B20LA18667
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 9/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 STARR CHEN
Corrections Issued 12/14/2020 STARR CHEN
Quality Review Completed 1/5/2021 HERNAN ARREOLA
Building Plans Picked Up 1/7/2021 APPLICANT
Plan Check Approved 4/8/2021 STARR CHEN
Issued 4/13/2021 APPLICANT
CofO in Progress 8/30/2021 EUGENE CASSIDY
Permit Finaled 9/11/2021 DEROLD HAUFF
CofO Issued 9/11/2021 DEROLD HAUFF
Permit Finaled 9/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/12/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/13/2021 CECILIO NAVARRO
Permit Cleared 1/13/2021 CECILIO NAVARRO
Sewer availability Cleared 1/20/2021 CECILIO NAVARRO
Trees in Parkway Cleared 1/25/2021 JOHN KIM
Hydrant and Access approval Cleared 1/29/2021 ROBERT DUFF
Low Impact Development Cleared 3/4/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 3/16/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 5/12/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval EUGENE CASSIDY
Insulation 5/13/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/17/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 6/17/2021 Approved JOHN KLARIN
Green Building Rough 6/17/2021 Approved JOHN KLARIN
HVAC-Rough 6/17/2021 Approved JOHN KLARIN
MERV13>=Rough 6/17/2021 Approved JOHN KLARIN
PLUMBING-Rough 6/17/2021 Approved JOHN KLARIN
Verify Sprinkler Sign Off 6/17/2021 Approved JOHN KLARIN
Insulation 6/18/2021 Approved EUGENE CASSIDY
Drywall Nailing 7/2/2021 Approved ANSON MAGLASANG
Interior/Exterior Lathing 7/2/2021 Approved ANSON MAGLASANG
ELECTRICAL-Final 8/23/2021 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Final 8/27/2021 Approved EUGENE CASSIDY
Final 8/27/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 8/27/2021 Approved EUGENE CASSIDY
HVAC-Final 8/27/2021 Approved EUGENE CASSIDY
MERV13>=Final 8/27/2021 Approved EUGENE CASSIDY
PLUMBING-Final 8/27/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/27/2021 Approved EUGENE CASSIDY
Smoke Detectors 8/27/2021 Approved EUGENE CASSIDY
Service/Power Release 8/30/2021 Approved EUGENE CASSIDY