2663 1/2 E ALICE ST 90065

Certificate Information: 2663 1/2 E ALICE ST 90065

Application / Permit
20010-10000-03667
Plan Check / Job No.
B20LA18655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED (N) 27'3" X 32'0" TWO STORY ACCESSORY DWELLING UNIT (1,200 SF max per Ordinance, LAMC 12.22 A.33(c) AND (d)) WITH AN ATTACHED TWO CAR GARAGE.
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
Issued on 3/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/23/2020 STANLEY RAAP
Corrections Issued 10/26/2020 STANLEY RAAP
Applicant returned to address corrections 2/20/2022 AUNG SOE
Plan Check Approved 2/23/2022 AUNG SOE
Issued 3/8/2022 APPLICANT
Building Plans Picked Up 3/11/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/1/2021 WALLIE JONG
Sewer availability Cleared 3/1/2021 WALLIE JONG
Miscellaneous Cleared 4/19/2021 DANIEL CORONADO
ZI Cleared 4/20/2021 DANIEL CORONADO
Grading Pre-Inspection Cleared 5/19/2021 KIRK LINKLATER
Hydrant and Access approval Cleared 5/26/2021 MATTHEW CRAIG
Low Impact Development Cleared 8/16/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/17/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 1/18/2022 NASHYA JENSEN
ZI Cleared 1/18/2022 NASHYA JENSEN
GPI Written Notices Cleared 2/18/2022 STANLEY RAAP

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/25/2022 Approved OSVALDO PARAMO
Pre-Inspection 8/19/2022 Approved OSVALDO PARAMO
Pre-Inspection 8/22/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 6/22/2023 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/13/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 7/18/2023 Partial Approval OSVALDO PARAMO
Underground Mechanical 7/21/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 9/11/2023 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 12/5/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/9/2024 Corrections Issued OSVALDO PARAMO
HVAC-Rough 5/9/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 5/17/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 5/17/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/20/2024 Approved OSVALDO PARAMO
Green Building Rough 5/20/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 5/20/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 8/2/2024 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 8/15/2024 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 8/28/2024 Not Ready for Inspection LUIS CASTRO
Shower Pan 8/28/2024 Corrections Issued LUIS CASTRO
Shower Pan 8/29/2024 Approved ALIZAH MAYAGOITIA
Insulation 9/17/2024 Approved JOHN QUINTANILLA
Drywall Nailing 9/27/2024 Approved JOHN QUINTANILLA
Service/Power Release 1/13/2025 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 7/17/2025 Approved GEM DE OCAMPO