2663 1/2 E ALICE ST 90065
Certificate Information: 2663 1/2 E ALICE ST 90065
- Application / Permit
- 20010-10000-03667
- Plan Check / Job No.
- B20LA18655
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED (N) 27'3" X 32'0" TWO STORY ACCESSORY DWELLING UNIT (1,200 SF max per Ordinance, LAMC 12.22 A.33(c) AND (d)) WITH AN ATTACHED TWO CAR GARAGE.
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- Issued on 3/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2020 | STANLEY RAAP |
| Corrections Issued | 10/26/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 2/20/2022 | AUNG SOE |
| Plan Check Approved | 2/23/2022 | AUNG SOE |
| Issued | 3/8/2022 | APPLICANT |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2021 | WALLIE JONG |
| Sewer availability | Cleared | 3/1/2021 | WALLIE JONG |
| Miscellaneous | Cleared | 4/19/2021 | DANIEL CORONADO |
| ZI | Cleared | 4/20/2021 | DANIEL CORONADO |
| Grading Pre-Inspection | Cleared | 5/19/2021 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 5/26/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/16/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/16/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 1/18/2022 | NASHYA JENSEN |
| ZI | Cleared | 1/18/2022 | NASHYA JENSEN |
| GPI Written Notices | Cleared | 2/18/2022 | STANLEY RAAP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2022 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 8/19/2022 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 8/22/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 7/18/2023 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 7/21/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 9/11/2023 | Conditional Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 12/5/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/9/2024 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 5/9/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/17/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/17/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 5/20/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/20/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/28/2024 | Not Ready for Inspection | LUIS CASTRO |
| Shower Pan | 8/28/2024 | Corrections Issued | LUIS CASTRO |
| Shower Pan | 8/29/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 9/17/2024 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 9/27/2024 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 1/13/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 7/17/2025 | Approved | GEM DE OCAMPO |