532 W 49TH ST A 90037
Certificate Information: 532 W 49TH ST A 90037
- Application / Permit
- 20010-10000-03663
- Plan Check / Job No.
- B20LA18646
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD (FRONT) APPROX: 1,988 SQ FT
- Permit Issued
- Issued on 10/20/2021
- Issuing Office
- Current Status
- CofO Issued on 6/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 11/17/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 11/25/2020 | KESETE HAREGOT |
| Plan Check Approved | 9/17/2021 | SERGIO GUTIERREZ |
| Issued | 10/20/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 6/21/2023 | BRENDAN MORELLI |
| CofO Issued | 6/25/2023 | DEROLD HAUFF |
| Permit Finaled | 6/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2020 | WALLIE JONG |
| Highway dedication | Cleared | 12/2/2020 | WALLIE JONG |
| Permit | Cleared | 12/2/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | WALLIE JONG |
| Sewer availability | Cleared | 12/3/2020 | WALLIE JONG |
| Low Impact Development | Cleared | 4/12/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/27/2021 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 5/12/2021 | PABLO ESTRADA |
| Stormwater Pollution Mitigatn | Cleared | 5/27/2021 | ORVAL HERNANDEZ-MARCI |
| Hydrant and Access approval | Cleared | 5/28/2021 | JOHN CONNEALLY |
Contact Information
| Engineer | Pinzon,, Eduardo A; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/3/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 12/3/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 12/8/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/9/2021 | Approved | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 1/27/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 7/27/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Rough | 7/27/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 7/27/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Rough | 8/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/15/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Rough | 8/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/15/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/15/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/11/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 10/14/2022 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 10/18/2022 | Partial Approval | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 10/18/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 10/25/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/8/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/8/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 11/8/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 11/14/2022 | Approved | RYAN SALAZAR |
| Insulation | 11/14/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | RYAN SALAZAR |
| MERV13>=Rough | 11/14/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 11/21/2022 | Approved | JULIAN AMAYA |
| Gas Test | 5/31/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 5/31/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| Final | 6/7/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| MERV13>=Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 6/7/2023 | Approved | BRENDAN MORELLI |
| Service/Power Release | 6/7/2023 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 6/7/2023 | Approved | BRENDAN MORELLI |