1213-1215 E 20TH ST 90011
Certificate Information: 1213-1215 E 20TH ST 90011
- Application / Permit
- 20010-10000-03626
- Plan Check / Job No.
- B20LA18462
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX -FRONT 1 OF 2
- Permit Issued
- Issued on 6/19/2021
- Issuing Office
- Current Status
- CofO Issued on 5/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | CARLOS MONTES |
| Corrections Issued | 11/10/2020 | CARLOS MONTES |
| Quality Review Completed | 11/30/2020 | WING SUEN |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Plan Check Approved | 4/23/2021 | CARLOS MONTES |
| Plan Check Approved | 5/5/2021 | CARLOS MONTES |
| Issued | 6/19/2021 | APPLICANT |
| CofO in Progress | 5/20/2022 | JOAQUIN GREENOUGH |
| No Progress | 5/20/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 5/20/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 5/20/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 5/24/2022 | DEROLD HAUFF |
| CofO Issued | 5/24/2022 | DEROLD HAUFF |
| Permit Finaled | 5/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 2/9/2021 | TERRI OSBORNE |
| Address approval | Cleared | 2/10/2021 | WALLIE JONG |
| Highway dedication | Cleared | 2/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/16/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/22/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/13/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/13/2021 | WALLIE JONG |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 7/28/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/3/2021 | Approved | JOAQUIN GREENOUGH |
| Pre-Inspection | 8/3/2021 | Partial Inspection | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/18/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/18/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/18/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/18/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 10/18/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/18/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/18/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/22/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 11/1/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 11/1/2021 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Sewer | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Rec and Parks Fee Memo | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 1/6/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 3/15/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Final | 3/15/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 5/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 5/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/16/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| MERV13>=Final | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 5/20/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |