2632 S HARCOURT AVE 90016

Certificate Information: 2632 S HARCOURT AVE 90016

Application / Permit
20010-10000-03622
Plan Check / Job No.
B20LA18435
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSEDDETACHED ACCESSORY DEWLLING UNIT AT REAR OF THE PROPERTY, ENGINEER DESIGN (PER 1200SF MAX PER ORDINANCE, LAMC 12.22 A 33 (C)-(D))
Permit Issued
Issued on 8/26/2021
Issuing Office
Current Status
Issued on 8/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/12/2020 APPLICANT
Assigned to Plan Check Engineer 10/19/2020 AUNG SOE
Corrections Issued 10/21/2020 AUNG SOE
Applicant returned to address corrections 8/12/2021 AUNG SOE
Plan Check Approved 8/13/2021 AUNG SOE
Building Plans Picked Up 8/17/2021 APPLICANT
Issued 8/26/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/25/2020 RENZ SORIANO
Construction near power lines Cleared 12/8/2020 RIDWAN HARDY
Address approval Cleared 2/4/2021 RENZ SORIANO
Sewer availability Cleared 2/8/2021 RENZ SORIANO
Hydrant and Access approval Cleared 3/26/2021 KURT CORRAL
Low Impact Development Cleared 7/7/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/11/2021 RENZ SORIANO

Contact Information

Contractor Perez Home Development; Lic. No.: 1060136-B P O BOX 898      GLENDORA, CA 91740
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/30/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 9/2/2021 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 9/2/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 9/2/2021 Approved STUART CHAPMAN
PLUMBING-Rough 9/2/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 9/13/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 9/13/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 9/17/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 10/20/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/21/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Partial Approval STUART CHAPMAN
Gas Test 10/21/2021 Partial Approval STUART CHAPMAN
Green Building Rough 10/21/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 10/21/2021 Approved STUART CHAPMAN
Special/Order Compliance 10/21/2021 Approved JOSE AVILA
Wood Frame 10/21/2021 Partial Approval STUART CHAPMAN
Deputy Wood Construction 10/22/2021 Conditional Approval STUART CHAPMAN
Underground Mechanical 10/25/2021 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 11/4/2021 Partial Approval AMY COLIN
Shower Pan 11/4/2021 Approved AMY COLIN
HVAC-Rough 11/12/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/7/2021 Approved STUART CHAPMAN
Green Building Rough 12/7/2021 Approved STUART CHAPMAN
Insulation 12/7/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 12/7/2021 Partial Approval STUART CHAPMAN
MERV13>=Rough 12/7/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 12/7/2021 Approved STUART CHAPMAN
Drywall Nailing 12/20/2021 Approved AMY COLIN
Interior/Exterior Lathing 12/23/2021 Approved STUART CHAPMAN
Pre-Inspection 1/13/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 1/13/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 2/17/2022 Partial Approval STUART CHAPMAN
Final 2/17/2022 Corrections Issued STUART CHAPMAN
Gas Test 2/17/2022 Approved STUART CHAPMAN
HVAC-Final 2/17/2022 Corrections Issued STUART CHAPMAN
Smoke Detectors 2/17/2022 Approved STUART CHAPMAN
Green Building Final 3/9/2022 Approved STUART CHAPMAN
PLUMBING-Final 3/9/2022 Approved STUART CHAPMAN
Service/Power Release 5/25/2022 Approved ANTHONY EGSON
Final 10/19/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 10/19/2022 Not Ready for Inspection STUART CHAPMAN
MERV13>=Final 10/19/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Approved STUART CHAPMAN