1753 S BEDFORD ST 90035

Certificate Information: 1753 S BEDFORD ST 90035

Application / Permit
20010-10000-03615
Plan Check / Job No.
B20LA18414
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD WITH ATTACHED 2 CAR GARAGE
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 1/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 CRYSTEL MAALOUF
Corrections Issued 1/5/2021 CRYSTEL MAALOUF
Quality Review Completed 2/3/2021 TU HUA
Building Plans Picked Up 3/23/2021 APPLICANT
Applicant returned to address corrections 5/27/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/11/2021 CRYSTEL MAALOUF
Plan Check Approved 6/30/2021 CRYSTEL MAALOUF
Issued 6/30/2021 APPLICANT
CofO in Progress 1/11/2022 EVAN COOPER
Permit Finaled 1/12/2022 DANIEL ORRANTE
CofO Issued 1/12/2022 DANIEL ORRANTE
Permit Finaled 1/12/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/3/2021 CELINA MORENO
Permit Cleared 3/3/2021 CELINA MORENO
Permit Cleared 3/3/2021 CELINA MORENO
Sewer availability Cleared 3/4/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/15/2021 CELINA MORENO
Hydrant and Access approval Cleared 4/29/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 6/18/2021 CELINA MORENO
Low Impact Development Cleared 6/25/2021 IDA MEISAMI-FARD
Frnt yard landscape/Water mgmt Cleared 6/29/2021 DANIEL CORONADO

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 28100 RIDGEFERN COURT      RANCHO PALOS VERDES, CA 90275
Contractor G M E Development; Lic. No.: 917664-B 2731 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2021 Approved EVAN COOPER
METHANE-Barrier 7/1/2021 Approved EVAN COOPER
METHANE-Subgrade 7/1/2021 Approved EVAN COOPER
PLUMBING-Rough 7/1/2021 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 7/6/2021 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Partial Approval EVAN COOPER
HVAC-Rough 8/12/2021 Approved EVAN COOPER
PLUMBING-Rough 8/16/2021 Corrections Issued KEVIN SARGSYAN
Shower Pan 8/16/2021 Approved KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 8/18/2021 Corrections Issued KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 8/23/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 8/25/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 8/25/2021 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 8/25/2021 Partial Approval EVAN COOPER
METHANE-Rough 8/25/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 8/25/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 8/31/2021 Approved EVAN COOPER
Green Building Rough 8/31/2021 Approved EVAN COOPER
Interior/Exterior Lathing 8/31/2021 Approved EVAN COOPER
Insulation 9/8/2021 Approved EVAN COOPER
Drywall Nailing 9/15/2021 Not Ready for Inspection EVAN COOPER
Drywall Nailing 9/20/2021 Approved EVAN COOPER
Final 10/8/2021 Not Ready for Inspection EVAN COOPER
Green Building Final 10/8/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready EVAN COOPER
Service/Power Release 10/8/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 10/8/2021 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 10/25/2021 Approved EVAN COOPER
ELECTRICAL-Final 11/16/2021 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 11/16/2021 Approved KEVIN SARGSYAN
HVAC-Final 11/16/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 11/16/2021 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 11/16/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 11/23/2021 Approved EVAN COOPER
HVAC-Final 11/23/2021 Approved EVAN COOPER
PLUMBING-Final 11/23/2021 Approved EVAN COOPER
Service/Power Release 11/23/2021 Approved EVAN COOPER
Final 12/3/2021 Corrections Issued EVAN COOPER
Green Building Final 12/3/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/3/2021 SGSOV Approved EVAN COOPER
Service/Power Release 12/3/2021 Approved EVAN COOPER
Smoke Detectors 12/3/2021 Approved EVAN COOPER
Final 1/11/2022 OK to Issue CofO EVAN COOPER