1753 S BEDFORD ST 90035
Certificate Information: 1753 S BEDFORD ST 90035
- Application / Permit
- 20010-10000-03615
- Plan Check / Job No.
- B20LA18414
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 1/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 1/5/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/3/2021 | TU HUA |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/11/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/30/2021 | CRYSTEL MAALOUF |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 1/11/2022 | EVAN COOPER |
| Permit Finaled | 1/12/2022 | DANIEL ORRANTE |
| CofO Issued | 1/12/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2021 | CELINA MORENO |
| Permit | Cleared | 3/3/2021 | CELINA MORENO |
| Permit | Cleared | 3/3/2021 | CELINA MORENO |
| Sewer availability | Cleared | 3/4/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/29/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 6/25/2021 | IDA MEISAMI-FARD |
| Frnt yard landscape/Water mgmt | Cleared | 6/29/2021 | DANIEL CORONADO |
Contact Information
| Architect | Leishman,, Thomas Edward; Lic. No.: C15059 | 28100 RIDGEFERN COURT RANCHO PALOS VERDES, CA 90275 |
| Contractor | G M E Development; Lic. No.: 917664-B | 2731 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2021 | Approved | EVAN COOPER |
| METHANE-Barrier | 7/1/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 7/1/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/1/2021 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 7/6/2021 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 8/12/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/16/2021 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 8/16/2021 | Approved | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 8/18/2021 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 8/23/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/25/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 8/25/2021 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 8/25/2021 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 8/25/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/25/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/31/2021 | Approved | EVAN COOPER |
| Green Building Rough | 8/31/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/31/2021 | Approved | EVAN COOPER |
| Insulation | 9/8/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 9/15/2021 | Not Ready for Inspection | EVAN COOPER |
| Drywall Nailing | 9/20/2021 | Approved | EVAN COOPER |
| Final | 10/8/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 10/8/2021 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/8/2021 | SGSOV Not Ready | EVAN COOPER |
| Service/Power Release | 10/8/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 10/8/2021 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 10/25/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 11/16/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 11/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 11/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Service/Power Release | 11/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/23/2021 | Approved | EVAN COOPER |
| HVAC-Final | 11/23/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 11/23/2021 | Approved | EVAN COOPER |
| Service/Power Release | 11/23/2021 | Approved | EVAN COOPER |
| Final | 12/3/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/3/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 12/3/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 12/3/2021 | Approved | EVAN COOPER |
| Final | 1/11/2022 | OK to Issue CofO | EVAN COOPER |