15505 W ROSCOE BLVD 91343
Certificate Information: 15505 W ROSCOE BLVD 91343
- Application / Permit
- 20010-10000-03604
- Plan Check / Job No.
- B20LA18398
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- 27'1" x 240'7" ADDITION TO (E) VEHICLE SERVICE BUILDING WHICH IS FOR THE EXISTING AUTO DEALERSHIP LOCATED AT 15505 ROSCOE BLVD. RESTROOM ADDED WTHIN EXISING BUILDING
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 12/1/2020 | APPLICANT |
| Corrections Issued | 12/17/2020 | HERNAN ARREOLA |
| Quality Review Completed | 12/17/2020 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 2/22/2021 | HERNAN ARREOLA |
| Green Plans Picked Up | 3/4/2021 | APPLICANT |
| Applicant returned to address corrections | 5/14/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/4/2021 | HERNAN ARREOLA |
| Plan Check Approved | 9/17/2021 | HERNAN ARREOLA |
| Issued | 9/27/2021 | APPLICANT |
| TCO Issued (Expire Date: 12-07-2022) | 6/10/2022 | JEFFREY DURAN |
| TCO Issued (Expire Date: 05-09-2023) | 11/10/2022 | JEFFREY DURAN |
| CofO in Progress | 4/25/2023 | ANDREW DORSO |
| Permit Finaled | 5/2/2023 | JEFFREY DURAN |
| CofO Issued | 5/2/2023 | JEFFREY DURAN |
| Permit Finaled | 5/2/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/5/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 2/5/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 2/5/2021 | DANIEL CORONADO |
| "T" removal | Cleared | 2/10/2021 | DANIEL CORONADO |
| DAS Clearance | Cleared | 2/18/2021 | CHOI YAN |
| Green Code | Cleared | 3/2/2021 | NEGAR NEJAD |
| Hydrant and Access approval | Cleared | 4/25/2021 | ROBERT DUFF |
| Automotive Use | Cleared | 5/25/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 7/27/2021 | JORGE MEJIA LEMUS |
| Highway dedication | Cleared | 8/25/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/26/2021 | DAGOVERTO GUERRERO |
| Permit | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Whitfield,, Gary Alan; Lic. No.: C8776 | 24691 DEL PRADO AVENUE SUITE 201 DANA POINT, CA 92629 |
| Contractor | Kunzik & Sara Construction Inc; Lic. No.: 847939-B | 1699 LA COSTA MEADOWS DR #102 SAN MARCOS, CA 92078 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 10/13/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/18/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 11/29/2021 | Conditional Approval | ANDREW DORSO |
| Masonry Wall/Backfill | 11/29/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 11/30/2021 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Masonry | 12/1/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 12/2/2021 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 12/3/2021 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 12/8/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 12/15/2021 | Not Ready for Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 12/20/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/5/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/6/2022 | Conditional Approval | ANDREW DORSO |
| Masonry Wall/Backfill | 1/6/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/7/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/11/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/12/2022 | Conditional Approval | ANDREW DORSO |
| Smoke Detectors | 1/12/2022 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/13/2022 | Conditional Approval | ANDREW DORSO |
| Final | 1/13/2022 | Corrections Issued | ANDREW DORSO |
| Green Building Rough | 1/13/2022 | Not Ready for Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 1/13/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Masonry | 1/14/2022 | Conditional Approval | DANIEL VARNUM |
| Masonry Wall/Backfill | 1/19/2022 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 1/20/2022 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 1/20/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 1/25/2022 | Conditional Approval | ANDREW DORSO |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | ANDREW DORSO |
| Structural Steel Frame | 2/1/2022 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 2/1/2022 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/2/2022 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 2/4/2022 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 2/4/2022 | Approved | ANDREW DORSO |
| Wood Frame | 2/9/2022 | Approved | ANDREW DORSO |
| Drywall Nailing | 5/27/2022 | Approved | ANDREW DORSO |
| Final | 5/27/2022 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 5/27/2022 | Approved | ANDREW DORSO |
| Green Building Final | 5/27/2022 | Approved | ANDREW DORSO |
| Reinforced Masonry Frame | 5/27/2022 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV No Gas | ANDREW DORSO |
| Smoke Detectors | 5/27/2022 | Approved | ANDREW DORSO |
| Structural Steel Frame | 5/27/2022 | Approved | ANDREW DORSO |
| Final | 9/30/2022 | Corrections Issued | ANDREW DORSO |
| Final | 11/9/2022 | OK for TCO | ANDREW DORSO |
| Special/Order Compliance | 4/24/2023 | Conditional Approval | ANDREW DORSO |
| Final | 4/25/2023 | OK to Issue CofO | ANDREW DORSO |