9043 W GIBSON ST 90034
Certificate Information: 9043 W GIBSON ST 90034
- Application / Permit
- 20010-10000-03599
- Plan Check / Job No.
- B20LA18391
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- CofO Issued on 7/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 10/17/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/13/2020 | MINYE PAK |
| Plan Check Approved | 12/18/2020 | ARSALAN SHABESTARI |
| Issued | 12/21/2020 | APPLICANT |
| CofO in Progress | 7/1/2021 | EVAN COOPER |
| Permit Finaled | 7/6/2021 | KENNETH NAGLE |
| CofO Issued | 7/6/2021 | KENNETH NAGLE |
| Permit Finaled | 7/6/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/21/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 11/9/2020 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 11/18/2020 | BARTON HOLMES |
| Construction near power lines | Cleared | 11/23/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | 8757 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Corrections Issued | EVAN COOPER |
| Wood Frame | 3/16/2021 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/9/2021 | Approved | EVAN COOPER |
| Sewer | 4/29/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Underground Mechanical | 4/29/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Underground Mechanical | 4/30/2021 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 5/12/2021 | Corrections Issued | EVAN COOPER |
| Underground Mechanical | 5/20/2021 | Corrections Issued | EVAN COOPER |
| Underground Mechanical | 5/24/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 5/26/2021 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Approved | EVAN COOPER |
| Final | 5/26/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/26/2021 | Approved | EVAN COOPER |
| Green Building Final | 5/26/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 5/26/2021 | Approved | EVAN COOPER |
| METHANE-Barrier | 5/26/2021 | Approved | EVAN COOPER |
| METHANE-Final | 5/26/2021 | Approved | EVAN COOPER |
| METHANE-Rough | 5/26/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 5/26/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Not Ready | EVAN COOPER |
| Service/Power Release | 5/26/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 5/26/2021 | No Access for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 5/26/2021 | Approved | EVAN COOPER |
| Sewer | 6/4/2021 | Approved | EVAN COOPER |
| Final | 6/24/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/24/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 6/24/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 6/24/2021 | Approved | EVAN COOPER |
| Verify Rec and Parks Fee Memo | 6/24/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 7/1/2021 | Approved | EVAN COOPER |
| Final | 7/1/2021 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 7/1/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 7/1/2021 | Approved | EVAN COOPER |
| Service/Power Release | 7/1/2021 | Approved | EVAN COOPER |