9043 W GIBSON ST 90034

Certificate Information: 9043 W GIBSON ST 90034

Application / Permit
20010-10000-03599
Plan Check / Job No.
B20LA18391
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028
Permit Issued
Issued on 12/21/2020
Issuing Office
Current Status
CofO Issued on 7/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ARSALAN SHABESTARI
Corrections Issued 10/17/2020 ARSALAN SHABESTARI
Quality Review Completed 11/13/2020 MINYE PAK
Plan Check Approved 12/18/2020 ARSALAN SHABESTARI
Issued 12/21/2020 APPLICANT
CofO in Progress 7/1/2021 EVAN COOPER
Permit Finaled 7/6/2021 KENNETH NAGLE
CofO Issued 7/6/2021 KENNETH NAGLE
Permit Finaled 7/6/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 10/21/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/21/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/4/2020 RENZ SORIANO
Sewer availability Cleared 11/9/2020 RENZ SORIANO
Grading Pre-Inspection Cleared 11/18/2020 BARTON HOLMES
Construction near power lines Cleared 11/23/2020 RIDWAN HARDY
Construction within easement Cleared 11/23/2020 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/2/2021 Corrections Issued EVAN COOPER
Wood Frame 3/16/2021 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/9/2021 Approved EVAN COOPER
Sewer 4/29/2021 Partial Inspection SHAVONNE ESPINOZA
Underground Mechanical 4/29/2021 Partial Inspection SHAVONNE ESPINOZA
Underground Mechanical 4/30/2021 Partial Approval EVAN COOPER
Underground Mechanical 5/12/2021 Corrections Issued EVAN COOPER
Underground Mechanical 5/20/2021 Corrections Issued EVAN COOPER
Underground Mechanical 5/24/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 5/26/2021 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/26/2021 Approved EVAN COOPER
Final 5/26/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 5/26/2021 Approved EVAN COOPER
Green Building Final 5/26/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 5/26/2021 Approved EVAN COOPER
METHANE-Barrier 5/26/2021 Approved EVAN COOPER
METHANE-Final 5/26/2021 Approved EVAN COOPER
METHANE-Rough 5/26/2021 Approved EVAN COOPER
METHANE-Subgrade 5/26/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Not Ready EVAN COOPER
Service/Power Release 5/26/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 5/26/2021 No Access for Inspection EVAN COOPER
Verify Sprinkler Sign Off 5/26/2021 Approved EVAN COOPER
Sewer 6/4/2021 Approved EVAN COOPER
Final 6/24/2021 Corrections Issued EVAN COOPER
Green Building Final 6/24/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved EVAN COOPER
Service/Power Release 6/24/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 6/24/2021 Approved EVAN COOPER
Verify Rec and Parks Fee Memo 6/24/2021 Approved EVAN COOPER
ELECTRICAL-Final 7/1/2021 Approved EVAN COOPER
Final 7/1/2021 OK to Issue CofO EVAN COOPER
HVAC-Final 7/1/2021 Approved EVAN COOPER
PLUMBING-Final 7/1/2021 Approved EVAN COOPER
Service/Power Release 7/1/2021 Approved EVAN COOPER