2157 W 70TH ST 90047
Certificate Information: 2157 W 70TH ST 90047
- Application / Permit
- 20010-10000-03598
- Plan Check / Job No.
- B20LA18390
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
- Permit Issued
- Issued on 1/12/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 10/17/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/13/2020 | MINYE PAK |
| Applicant returned to address corrections | 12/14/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/8/2021 | ARSALAN SHABESTARI |
| Issued | 1/12/2021 | APPLICANT |
| CofO in Progress | 8/6/2021 | FREDDIE RIVERA |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
| CofO Issued | 8/10/2021 | DEROLD HAUFF |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/21/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 11/4/2020 | RENZ SORIANO |
| Construction near power lines | Cleared | 12/16/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/16/2020 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/19/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/15/2021 | No Access for Inspection | FREDDIE RIVERA |
| Wood Frame | 3/18/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/14/2021 | Conditional Approval | FREDDIE RIVERA |
| Sewer | 4/14/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 4/16/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 5/3/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 5/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Underground Mechanical | 6/15/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/2/2021 | Approved | FREDDIE RIVERA |
| Final | 7/2/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/2/2021 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/2/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 7/2/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 7/2/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 7/2/2021 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 7/2/2021 | Approved | FREDDIE RIVERA |