2812 S MALCOLM AVE 90064

Certificate Information: 2812 S MALCOLM AVE 90064

Application / Permit
20010-10000-03596
Plan Check / Job No.
B20LA18388
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
Permit Issued
Issued on 12/23/2020
Issuing Office
Current Status
CofO Issued on 6/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ARSALAN SHABESTARI
Corrections Issued 10/17/2020 ARSALAN SHABESTARI
Quality Review Completed 11/13/2020 MINYE PAK
Applicant returned to address corrections 11/24/2020 ARSALAN SHABESTARI
Plan Check Approved 12/21/2020 ARSALAN SHABESTARI
Issued 12/23/2020 APPLICANT
CofO in Progress 6/30/2021 KENNETH NAGLE
Permit Finaled 6/30/2021 KENNETH NAGLE
CofO Issued 6/30/2021 KENNETH NAGLE
Permit Finaled 6/30/2021 KENNETH NAGLE

Permit Application Clearance Information

Construction near power lines Cleared 10/21/2020 RIDWAN HARDY
Construction within easement Cleared 10/21/2020 RIDWAN HARDY
Address approval Cleared 10/28/2020 DINAH GARIN
Specific Plan Cleared 10/29/2020 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 10/30/2020 DINAH GARIN
Sewer availability Cleared 10/30/2020 DINAH GARIN
Grading Pre-Inspection Cleared 11/18/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 11/24/2020 DINAH GARIN

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/24/2021 Conditional Approval RICHARD ROBLES
Wood Frame 3/16/2021 No Access for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/19/2021 No Access for Inspection EVAN COOPER
Wood Frame 3/23/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 4/12/2021 Approved EVAN COOPER
Wood Frame 4/12/2021 Approved EVAN COOPER
Sewer 4/21/2021 Corrections Issued KENNETH NAGLE
Underground Mechanical 4/27/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/27/2021 Approved OGANES TARAKHCHYAN
Final 5/27/2021 Partial Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/27/2021 Approved OGANES TARAKHCHYAN
Green Building Final 5/27/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 5/27/2021 Approved OGANES TARAKHCHYAN
MERV13>=Final 5/27/2021 Approved OGANES TARAKHCHYAN
MERV13>=Rough 5/27/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV No Gas OGANES TARAKHCHYAN
Service/Power Release 5/27/2021 Approved OGANES TARAKHCHYAN
Smoke Detectors 5/27/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 5/27/2021 Approved OGANES TARAKHCHYAN
Final 6/30/2021 Conditional Approval KENNETH NAGLE