2613 S BENTLEY AVE 90064

Certificate Information: 2613 S BENTLEY AVE 90064

Application / Permit
20010-10000-03594
Plan Check / Job No.
B20LA18386
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 9/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ARSALAN SHABESTARI
Corrections Issued 10/16/2020 ARSALAN SHABESTARI
Quality Review Completed 11/13/2020 MINYE PAK
Applicant returned to address corrections 12/14/2020 ARSALAN SHABESTARI
Plan Check Approved 1/8/2021 ARSALAN SHABESTARI
Issued 1/12/2021 APPLICANT
CofO in Progress 9/28/2021 KENNETH NAGLE
Permit Finaled 9/28/2021 KENNETH NAGLE
CofO Issued 9/28/2021 KENNETH NAGLE
Permit Finaled 9/28/2021 KENNETH NAGLE

Permit Application Clearance Information

Specific Plan Cleared 10/27/2020 PEDRO AYALA
Address approval Cleared 11/2/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/6/2020 DINAH GARIN
Sewer availability Cleared 11/6/2020 DINAH GARIN
Grading Pre-Inspection Cleared 11/18/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 12/4/2020 DINAH GARIN
Construction near power lines Cleared 12/16/2020 RIDWAN HARDY
Construction within easement Cleared 12/16/2020 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/19/2021 Approved EVAN COOPER
Underground Mechanical 4/27/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/3/2021 Conditional Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Conditional Approval KENNETH NAGLE
Green Building Rough 5/3/2021 Approved KENNETH NAGLE
MERV13>=Rough 5/3/2021 Approved KENNETH NAGLE
METHANE-Rough 5/3/2021 Approved KENNETH NAGLE
Verify Sprinkler Sign Off 5/3/2021 Approved KENNETH NAGLE
Grounding or Bonding 5/11/2021 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 5/11/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Final 5/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 5/27/2021 Approved OGANES TARAKHCHYAN
MERV13>=Final 5/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Barrier 5/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Subgrade 5/27/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 5/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Smoke Detectors 5/27/2021 Approved OGANES TARAKHCHYAN
Grounding or Bonding 6/4/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Rec and Parks Fee Memo 6/4/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/7/2021 Approved EVAN COOPER
Final 9/7/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 9/7/2021 Approved EVAN COOPER
MERV13>=Final 9/7/2021 Approved EVAN COOPER
METHANE-Barrier 9/7/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Approved EVAN COOPER
Service/Power Release 9/7/2021 Approved EVAN COOPER