445 N AVALON BLVD 90744

Certificate Information: 445 N AVALON BLVD 90744

Application / Permit
20010-10000-03580
Plan Check / Job No.
B20LA18313
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY TYPE IIIA 74 UNITS 100% AFFORDABLE HOUSING APARTMENT PER LAMC 14.00 A13 QPSH
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Issued 11/5/2021 APPLICANT
Building Plans Picked Up 11/12/2021 APPLICANT
TCO Issued (Expire Date: 07-20-2025) 1/21/2025 JOEY BUCHANAN
CofO in Progress 1/31/2025 JOEY BUCHANAN
Permit Finaled 2/13/2025 HENRY BAGHDASSARIAN
CofO Issued 2/13/2025 HENRY BAGHDASSARIAN
Permit Finaled 2/13/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 11/17/2020 CHINH DINH
Highway dedication Cleared 12/1/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 12/2/2020 CHINH DINH
Hydrant and Access approval Cleared 12/16/2020 MATTHEW CRAIG
Building over 36-ft Cleared 1/5/2021 CALOSHA APPROVED
"Q" conditions Cleared 2/26/2021 ULISES GONZALEZ
Miscellaneous Cleared 2/26/2021 ULISES GONZALEZ
Miscellaneous Cleared 2/26/2021 ULISES GONZALEZ
Miscellaneous Cleared 2/26/2021 ULISES GONZALEZ
Green Code Cleared 4/5/2021 KEVIN MORALES
Sewer availability Cleared 4/14/2021 CHINH DINH
Low Impact Development Cleared 5/5/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 5/6/2021 CHINH DINH
Construction near power lines Cleared 5/11/2021 RIDWAN HARDY
"Q" conditions Cleared 5/21/2021 ULISES GONZALEZ
Clean Up Green Up Cleared 5/21/2021 ULISES GONZALEZ
Methane Ordinance Cleared 5/21/2021 ANDREW KO
Miscellaneous Cleared 5/21/2021 ULISES GONZALEZ
Opn space landscape/Water mgmt Cleared 5/21/2021 ULISES GONZALEZ
Fire Marshal Fire Life Safety Cleared 6/23/2021 OSCAR SALGADO JR
DAS Clearance Cleared 7/9/2021 ELIZABETH TOMS
Density Bonus 14.00.A.13 Cleared 9/14/2021 JAMES MCCARTHY
Permanent Supportive Housing Cleared 10/4/2021 GISELLE CORELLA

Contact Information

Architect El, Bayar, Sami M; Lic. No.: C26080 22834 BRENFORD STREET      WOODLAND HILLS, CA 91364
Contractor Trg Construction Inc; Lic. No.: 1069375-B 329 PACIFIC COAST HWY      HERMOSA BEACH, CA 90254
Engineer Heydar,, Ahmad; Lic. No.: S3679 28025 DOROTHY DR STE 104      AGOURA HILLS, CA 91301

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/18/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 6/23/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 6/28/2022 Corrections Issued JOEY BUCHANAN
METHANE-Barrier 6/28/2022 Not Ready for Inspection JOEY BUCHANAN
METHANE-Subgrade 6/28/2022 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 7/1/2022 Not Ready for Inspection DAVID TSAU
METHANE-Barrier 7/1/2022 Not Ready for Inspection DAVID TSAU
METHANE-Subgrade 7/1/2022 Not Ready for Inspection DAVID TSAU
Footing/Foundation/Slab 7/11/2022 Partial Approval JOEY BUCHANAN
METHANE-Barrier 7/11/2022 Not Ready for Inspection JOEY BUCHANAN
METHANE-Subgrade 7/11/2022 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 7/13/2022 Approved JOEY BUCHANAN
Deputy Methane Barrier 7/22/2022 Approved JOEY BUCHANAN
Deputy Methane Barrier 7/29/2022 Conditional Approval DAVID TSAU
METHANE-Subgrade 8/10/2022 Partial Approval DAVID TSAU
Deputy Drilled-In Anchors 8/11/2022 Conditional Approval DAVID TSAU
Deputy Drilled-In Anchors 8/12/2022 Conditional Approval DAVID TSAU
Deputy Steel/Welding 8/12/2022 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 8/22/2022 Corrections Issued JOEY BUCHANAN
METHANE-Barrier 8/22/2022 Not Ready for Inspection JOEY BUCHANAN
METHANE-Subgrade 8/22/2022 Not Ready for Inspection JOEY BUCHANAN
METHANE-Rough 8/24/2022 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 8/26/2022 Approved JOEY BUCHANAN
Deputy Methane Barrier 9/1/2022 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 9/7/2022 Conditional Approval TED RIES
Footing/Foundation/Slab 9/8/2022 Partial Approval TED RIES
METHANE-Barrier 9/8/2022 Partial Approval TED RIES
METHANE-Subgrade 9/8/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 9/19/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 9/19/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 9/20/2022 Conditional Approval TED RIES
Deputy Steel/Welding 9/21/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/22/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 9/22/2022 Approved JOEY BUCHANAN
METHANE-Barrier 9/22/2022 Approved JOEY BUCHANAN
METHANE-Subgrade 9/22/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/23/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/26/2022 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 9/27/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/27/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/29/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/30/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/3/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/4/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/5/2022 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 10/6/2022 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 10/7/2022 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 10/8/2022 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 10/11/2022 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 10/12/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/17/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/18/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/19/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/20/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 10/25/2022 Approved JOEY BUCHANAN
Deputy Wood Construction 11/2/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval JOEY BUCHANAN
Pre-Inspection 11/4/2022 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 11/14/2022 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 11/21/2022 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/22/2022 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 11/22/2022 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 12/20/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 2/13/2023 Approved JOEY BUCHANAN
Deputy Wood Construction 2/22/2023 Conditional Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 2/24/2023 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 3/20/2023 Approved JOEY BUCHANAN
Deputy Steel/Welding 3/24/2023 Approved JOEY BUCHANAN
Deputy Steel/Welding 3/31/2023 Approved JOEY BUCHANAN
Deputy Wood Construction 4/6/2023 Approved JOEY BUCHANAN
Wall Anchors 4/6/2023 Not Ready for Inspection JOEY BUCHANAN
Deputy Wood Construction 4/7/2023 Approved JOEY BUCHANAN
Wall Anchors 4/10/2023 Partial Approval JOEY BUCHANAN
Drywall Nailing 4/14/2023 Approved AMANUEL BERHE
Green Building Rough 4/14/2023 Approved AMANUEL BERHE
Deputy Wood Construction 4/27/2023 Approved JOEY BUCHANAN
METHANE-Rough 5/1/2023 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 5/1/2023 Approved JOEY BUCHANAN
Wood Frame 5/1/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 5/8/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Partial Approval JOEY BUCHANAN
Insulation 5/23/2023 Corrections Issued JOEY BUCHANAN
Interior/Exterior Lathing 6/6/2023 Partial Approval JOEY BUCHANAN
Insulation 7/7/2023 Partial Inspection AMANUEL BERHE
Insulation 7/20/2023 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 7/26/2023 Approved JOEY BUCHANAN
Insulation 8/1/2023 Partial Approval JOEY BUCHANAN
Insulation 8/18/2023 Partial Approval JOEY BUCHANAN
Pre-Inspection 8/23/2023 Approved JOEY BUCHANAN
Deputy Wood Construction 8/25/2023 Conditional Approval AMANUEL BERHE
Insulation 8/28/2023 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Partial Inspection AMANUEL BERHE
Insulation 9/19/2023 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 9/28/2023 Approved AMANUEL BERHE
Wood Frame 9/28/2023 Partial Inspection AMANUEL BERHE
Insulation 10/5/2023 Partial Approval JOEY BUCHANAN
Wood Frame 10/12/2023 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 10/31/2023 Corrections Issued JOEY BUCHANAN
Deputy Wood Construction 11/2/2023 Conditional Approval AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 11/13/2023 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 11/16/2023 Partial Approval JOEY BUCHANAN
Wood Frame 11/27/2023 Partial Approval JOEY BUCHANAN
Insulation 12/20/2023 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 1/8/2024 Approved JOEY BUCHANAN
Insulation 1/11/2024 Partial Inspection AMANUEL BERHE
Special/Order Compliance 1/17/2024 Approved JOEY BUCHANAN
Insulation 1/22/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 1/22/2024 Approved JOEY BUCHANAN
Special/Order Compliance 1/31/2024 Not Ready for Inspection AMANUEL BERHE
Special/Order Compliance 2/6/2024 Approved JOEY BUCHANAN
Insulation 2/28/2024 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 3/12/2024 Conditional Approval AMANUEL BERHE
Insulation 3/14/2024 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 3/15/2024 Approved JOEY BUCHANAN
Footing/Foundation/Slab 3/20/2024 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 3/22/2024 Approved JOEY BUCHANAN
Deputy Wood Construction 3/26/2024 Approved JOEY BUCHANAN
Special/Order Compliance 3/26/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 3/29/2024 Partial Inspection AMANUEL BERHE
Special/Order Compliance 4/1/2024 Not Ready for Inspection AMANUEL BERHE
Deputy Wood Construction 4/3/2024 Approved AMANUEL BERHE
Special/Order Compliance 4/4/2024 Partial Inspection AMANUEL BERHE
Drywall Nailing 4/9/2024 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 4/15/2024 Approved JOEY BUCHANAN
Drywall Nailing 4/25/2024 Partial Approval JOEY BUCHANAN
Drywall Nailing 5/14/2024 Partial Approval JOEY BUCHANAN
Drywall Nailing 6/17/2024 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 6/24/2024 Approved JOEY BUCHANAN
Drywall Nailing 8/1/2024 Partial Approval JOEY BUCHANAN
Drywall Nailing 8/21/2024 Corrections Issued JOEY BUCHANAN
Drywall Nailing 8/23/2024 Partial Approval JOEY BUCHANAN
Drywall Nailing 9/17/2024 Partial Approval JOEY BUCHANAN
Special/Order Compliance 10/22/2024 Approved JOEY BUCHANAN
Drywall Nailing 11/25/2024 Approved JOEY BUCHANAN
Final 11/25/2024 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 11/25/2024 Approved JOEY BUCHANAN
Reinforced Masonry Frame 11/25/2024 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 11/25/2024 Approved JOEY BUCHANAN
Wood Frame 11/25/2024 Approved JOEY BUCHANAN
Pre-Inspection 11/26/2024 Approved JOEY BUCHANAN
Final 12/23/2024 Corrections Issued JOEY BUCHANAN
Pre-Inspection 1/13/2025 Approved JOEY BUCHANAN
Final 1/31/2025 OK to Issue CofO JOEY BUCHANAN