592 N TIGERTAIL ROAD 90049

Certificate Information: 592 N TIGERTAIL ROAD 90049

Application / Permit
20010-10000-03567
Plan Check / Job No.
B20LA18228
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family dwelling
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 SHANGQIN XIE
Corrections Issued 11/10/2020 SHANGQIN XIE
Quality Review Completed 11/20/2020 STANLEY RAAP
Applicant returned to address corrections 6/29/2021 SHANGQIN XIE
Applicant returned to address corrections 9/23/2021 SHANGQIN XIE
Applicant returned to address corrections 12/16/2021 SHANGQIN XIE
Applicant returned to address corrections 4/12/2022 SHANGQIN XIE
Applicant returned to address corrections 4/18/2022 SHANGQIN XIE
Plan Check Approved 4/19/2022 SHANGQIN XIE
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/9/2022 APPLICANT
CofO in Progress 9/23/2025 MICHAEL PELHAM
Permit Finaled 9/24/2025 RICHARD STEINBACH
CofO Issued 9/24/2025 RICHARD STEINBACH
Permit Finaled 9/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/11/2021 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 2/11/2021 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 2/11/2021 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 2/11/2021 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 2/11/2021 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 2/11/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 2/16/2021 CATHERINE ADROVER
Sewer availability Cleared 2/17/2021 CATHERINE ADROVER
Miscellaneous Cleared 9/15/2021 DENZEL HENDERSON
Low Impact Development Cleared 10/20/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/8/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 11/9/2021 MATTHEW CRAIG

Contact Information

Architect De, La Nuez, George; Lic. No.: C25705 28025 DOROTHY DR SUITE 100      AGOURA HILLS, CA 91301
Contractor Oakhill Construction Inc; Lic. No.: 1013979-B 23679 CALABASAS ROAD #1111      CALABASAS, CA 91302
Engineer Cox,, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/22/2022 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/30/2022 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 8/30/2022 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/30/2022 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 10/4/2022 Not Ready for Inspection MICHAEL PELHAM
Special/Order Compliance 10/4/2022 Corrections Issued MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 10/7/2022 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 10/7/2022 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 10/24/2022 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 11/3/2022 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 11/3/2022 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/15/2022 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 12/20/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/21/2022 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 12/22/2022 No Access for Inspection ROBERT SUNSERI
Deputy Reinf. Concrete 1/17/2023 Corrections Issued ROBERT SUNSERI
Excavation/Setback/Form/Re-Bar 1/20/2023 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 1/24/2023 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 1/24/2023 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 1/24/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/31/2023 Not Ready for Inspection CARLOS MATAMOROS
Piling/Pier/Caisson 1/31/2023 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Concrete Frame 1/31/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 2/15/2023 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 2/22/2023 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/2/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/20/2023 Corrections Issued STEPHANIE SWANSON
Deputy Reinf. Concrete 3/28/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/28/2023 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 4/28/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/3/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/5/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/11/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/7/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/16/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 6/28/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/28/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 7/3/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/5/2023 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/7/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 7/13/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/17/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 8/2/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/1/2023 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 9/1/2023 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 9/1/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/5/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/8/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/20/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/25/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/6/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/10/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Steel/Welding 10/27/2023 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/13/2023 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 11/14/2023 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 12/6/2023 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 12/8/2023 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 12/8/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/11/2023 Partial Approval CARLOS MATAMOROS
Reinforced Masonry Frame 12/11/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 12/19/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 1/8/2024 Partial Approval CARLOS MATAMOROS
Structural Steel Frame 1/8/2024 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/8/2024 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 1/10/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/8/2024 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 3/11/2024 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/11/2024 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval CARLOS MATAMOROS
Pre-Inspection 4/12/2024 Partial Approval CARLOS MATAMOROS
Special/Order Compliance 4/12/2024 Approved CARLOS MATAMOROS
Gas Test 4/18/2024 Approved CARLOS MATAMOROS
Underground Mechanical 4/18/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Not Ready for Inspection CARLOS MATAMOROS
Deputy Wood Construction 4/23/2024 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Partial Approval CARLOS MATAMOROS
Sewer 5/17/2024 Partial Approval CARLOS MATAMOROS
Gas Test 5/21/2024 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 5/21/2024 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 6/21/2024 Approved CARLOS MATAMOROS
Sewer 7/3/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Approved CARLOS MATAMOROS
Gas Test 7/12/2024 Partial Approval CARLOS MATAMOROS
HVAC-Rough 7/12/2024 Approved CARLOS MATAMOROS
Underground Mechanical 7/12/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/22/2024 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 7/23/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 7/31/2024 Corrections Issued CARLOS MATAMOROS
Shower Pan 8/8/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 8/9/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 8/9/2024 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 8/12/2024 Conditional Approval CARLOS MATAMOROS
Green Building Rough 8/12/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 8/12/2024 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 8/12/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 8/14/2024 Approved CARLOS MATAMOROS
Insulation 8/22/2024 Partial Approval CARLOS MATAMOROS
Insulation 9/5/2024 No Access for Inspection CARLOS MATAMOROS
Drywall Nailing 9/13/2024 Partial Approval CARLOS MATAMOROS
Insulation 9/13/2024 Approved CARLOS MATAMOROS
Drywall Nailing 9/24/2024 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 9/27/2024 Approved CARLOS MATAMOROS
Drywall Nailing 10/10/2024 Approved CARLOS MATAMOROS
Sewer 2/21/2025 Partial Approval CARLOS MATAMOROS
Gas Test 2/25/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 2/25/2025 Partial Approval CARLOS MATAMOROS
Pre-Inspection 3/24/2025 Approved CARLOS MATAMOROS
Sewer 5/1/2025 Partial Approval CARLOS MATAMOROS
Gas Test 5/7/2025 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 5/7/2025 Approved CARLOS MATAMOROS
Underground Mechanical 5/7/2025 Approved CARLOS MATAMOROS
Gas Test 5/8/2025 Approved CARLOS MATAMOROS
Gas Test 5/15/2025 Approved CARLOS MATAMOROS
HVAC-Final 5/16/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Final 5/19/2025 Partial Approval BOBBY KEY
ELECTRICAL-Final 5/21/2025 Approved CARLOS MATAMOROS
HVAC-Final 5/21/2025 Approved CARLOS MATAMOROS
Service/Power Release 5/22/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 5/27/2025 Permit Expired CARLOS MATAMOROS
PLUMBING-Rough 6/13/2025 Partial Approval CARLOS MATAMOROS
Underground Mechanical 6/13/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/17/2025 Approved CARLOS MATAMOROS
Final 9/17/2025 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 9/17/2025 Approved CARLOS MATAMOROS
Green Building Final 9/17/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/17/2025 Approved CARLOS MATAMOROS
Structural Steel Frame 9/17/2025 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 9/23/2025 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 9/23/2025 Approved MICHAEL PELHAM
Final 9/23/2025 OK to Issue CofO MICHAEL PELHAM