6709 S 3RD AVE 90043

Certificate Information: 6709 S 3RD AVE 90043

Application / Permit
20010-10000-03566
Plan Check / Job No.
B20LA18209
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New, one-story Accesory Dwelling Unit per LAMC 12.22 A.33(c) and (d) (30'-0" X 25'-0", 750 SF). All work per WFPP.
Permit Issued
Issued on 1/15/2022
Issuing Office
Current Status
Issued on 1/15/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 CHRISTOPHER KOMANCHECK
Corrections Issued 10/15/2020 CHRISTOPHER KOMANCHECK
Plan Check Approved 12/1/2021 RICARDO RAMIREZ
Issued 1/15/2022 APPLICANT
Building Plans Picked Up 1/26/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/10/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/7/2021 WALLIE JONG
Sewer availability Cleared 6/7/2021 WALLIE JONG
Hydrant and Access approval Cleared 7/6/2021 KURT CORRAL
Construction near power lines Cleared 7/19/2021 RIDWAN HARDY
Low Impact Development Cleared 10/20/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 11/15/2021 STEVE MELGAR

Contact Information

Contractor Sutton Home Improvement; Lic. No.: 830509-B 914 NORTH DWIGHT AVE      COMPTON, CA 90220
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/1/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/10/2022 Corrections Issued FREDDIE RIVERA
Pre-Inspection 3/21/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 8/15/2022 Corrections Issued ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 8/22/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 9/16/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/25/2022 No Access for Inspection ALIZAH MAYAGOITIA
Green Building Rough 10/25/2022 No Access for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 10/25/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/5/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 2/8/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/8/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 4/11/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 4/11/2023 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 4/14/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/14/2023 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 4/19/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/19/2023 Approved ENRIQUE MIRELES
Green Building Rough 4/19/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/19/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/19/2023 Approved ENRIQUE MIRELES
Service/Power Release 8/21/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Not Ready ENRIQUE MIRELES
Final 10/11/2023 Corrections Issued ENRIQUE MIRELES
Pre-Inspection 10/11/2023 Approved ENRIQUE MIRELES
Drywall Nailing 10/20/2023 Approved ENRIQUE MIRELES
Final 10/20/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 10/20/2023 Approved ENRIQUE MIRELES
Green Building Final 10/20/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/20/2023 Approved ENRIQUE MIRELES
Underground Mechanical 11/22/2023 Approved ENRIQUE MIRELES