851 N ALMA REAL DR 90272
Certificate Information: 851 N ALMA REAL DR 90272
- Application / Permit
- 20010-10000-03564
- Plan Check / Job No.
- B20LA18207
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW MODULAR RESTROOMS BLDG. PARKING IMPROVEMENT AND LANDSCAPING -RESTORATION AND PARK- 1 OF 2
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofO Issued on 12/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 10/19/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/28/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 6/14/2021 | APPLICANT |
| Applicant returned to address corrections | 6/24/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/15/2021 | SERGIO GUTIERREZ |
| Issued | 7/15/2021 | APPLICANT |
| CofO in Progress | 12/8/2022 | DERRICK SPENCER |
| Permit Finaled | 12/9/2022 | DAVID TSAU |
| CofO Issued | 12/9/2022 | DAVID TSAU |
| Permit Finaled | 12/9/2022 | DAVID TSAU |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 12/8/2020 | HAROOT AVANESIAN |
| Green Code | Cleared | 12/8/2020 | SERGIO GUTIERREZ |
| Certificate of Compliance | Cleared | 12/16/2020 | MARC WOERSCHING |
| Grading Pre-Inspection | Cleared | 12/17/2020 | SERGIO GUTIERREZ |
| Coastal Zone | Cleared | 12/29/2020 | MAXFIELD VERMY |
| Address approval | Cleared | 1/21/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/2/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 2/3/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 4/26/2021 | MARTIN FRAGOSO |
| Stormwater Pollution Mitigatn | Cleared | 4/26/2021 | MARTIN FRAGOSO |
| DAS Clearance | Cleared | 6/10/2021 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Ford E C Inc; Lic. No.: 396212-B | 10850 WILSHIRE BLVD #380 LOS ANGELES, CA 90024 |
| Engineer | Chaudhary,, Muhammad Riaz; Lic. No.: C48177 | 340 E COMMONWEALTH AVE FULLERTON, CA 92832 |
| Landscape Architect | Sherrod,, Michael S; Lic. No.: LA4320 | 938 ANCHOR ST MORRO BAY, CA 93442 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2021 | Partial Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 11/2/2021 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/9/2021 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/17/2021 | Approved | DERRICK SPENCER |
| Deputy Grading | 11/22/2021 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/7/2021 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/8/2021 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/9/2021 | Approved | DERRICK SPENCER |
| Deputy Grading | 12/10/2021 | Approved | DERRICK SPENCER |
| Pre-Inspection | 2/17/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/23/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 3/7/2022 | Approved | DERRICK SPENCER |
| Final | 6/13/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/13/2022 | Partial Approval | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 6/13/2022 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 6/13/2022 | Approved | DERRICK SPENCER |
| Wood Frame | 6/13/2022 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 7/12/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/1/2022 | Partial Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 8/1/2022 | Approved | DERRICK SPENCER |
| Deputy Methane Barrier | 8/2/2022 | Approved | DERRICK SPENCER |
| Deputy Other (see comments) | 8/2/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/2/2022 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 9/19/2022 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 10/31/2022 | Partial Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 11/18/2022 | Approved | DERRICK SPENCER |
| Final | 11/30/2022 | No Access for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 11/30/2022 | Approved | DERRICK SPENCER |
| Final | 12/7/2022 | OK to Issue CofO | DERRICK SPENCER |