3664 S BERRYMAN AVE 90066
Certificate Information: 3664 S BERRYMAN AVE 90066
- Application / Permit
- 20010-10000-03551
- Plan Check / Job No.
- B20LA18188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING TWO STORY HOUSE WITH ATTACHED GARAGE
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/21/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/4/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| Plan Check Approved | 3/12/2021 | MAHNAZ NOURHASHEMI |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 4/7/2022 | JOHNNY MIRANDA |
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
| CofO Issued | 4/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2020 | DINAH GARIN |
| Permit | Cleared | 12/18/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/15/2021 | DINAH GARIN |
| Specific Plan | Cleared | 1/28/2021 | FREDDY GARCIA |
| Low Impact Development | Cleared | 2/8/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/9/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/2/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/10/2021 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 3/10/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 4/28/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/6/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | KENNETH NAGLE |
| Deputy Wood Construction | 6/22/2021 | Conditional Approval | AMY COLIN |
| Wood Frame | 6/28/2021 | Partial Approval | JACK MATTILLO |
| HVAC-Rough | 7/28/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/29/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/29/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | EVAN COOPER |
| Green Building Rough | 8/3/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 8/3/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/3/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/3/2021 | Approved | EVAN COOPER |
| Wood Frame | 8/3/2021 | Approved | EVAN COOPER |
| Insulation | 8/10/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 8/12/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/19/2021 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 8/30/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/26/2022 | No Access for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 1/26/2022 | No Access for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 1/28/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 1/28/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/25/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 2/25/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA |
| Service/Power Release | 2/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 4/5/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 4/5/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 4/5/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Service/Power Release | 4/5/2022 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/5/2022 | Approved | JOHNNY MIRANDA |
| Final | 4/6/2022 | OK to Issue CofO | JOHNNY MIRANDA |
| PLUMBING-Final | 4/6/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | JOHNNY MIRANDA |