14945 W CHATSWORTH ST 91345
Certificate Information: 14945 W CHATSWORTH ST 91345
- Application / Permit
- 20010-10000-03508
- Plan Check / Job No.
- B20LA18136
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | CARLOS MONTES |
| Corrections Issued | 12/3/2020 | CARLOS MONTES |
| Quality Review Completed | 12/22/2020 | WING SUEN |
| Plan Check Approved | 3/15/2021 | CARLOS MONTES |
| Issued | 3/19/2021 | APPLICANT |
| CofO in Progress | 10/1/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/13/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/14/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/14/2021 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 1/14/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 2/23/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | E G N Builders Group; Lic. No.: 1051430-B | 5000 PARKWAY CALABASAS SUITE 308 CALABASAS, CA 91302 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 4/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 4/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/19/2021 | Approved | JENNIFER RABUCHIN |
| Gas Test | 4/19/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Sewer | 4/19/2021 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 4/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/20/2021 | Partial Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 5/20/2021 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/20/2021 | Partial Inspection | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 5/26/2021 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/2/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/2/2021 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/2/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/2/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 6/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Drywall Nailing | 6/21/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/8/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 9/28/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 9/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 9/28/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/28/2021 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/28/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/1/2021 | Approved | JENNIFER RABUCHIN |
| Final | 10/1/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 10/1/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/1/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/1/2021 | Approved | JENNIFER RABUCHIN |