8649 N RINCON AVE 91352
Certificate Information: 8649 N RINCON AVE 91352
- Application / Permit
- 20010-10000-03470
- Plan Check / Job No.
- B20LA18036
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** New 42'-0" x 34'-8" detached, 1-story Accessory Dwelling Unit per LAMC 12.22A.33(c)(d) &(g). All work per Wood Frame Prescriptive Design. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- Issued on 2/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | ZAW HAN |
| Corrections Issued | 11/9/2020 | ZAW HAN |
| Quality Review Completed | 12/8/2020 | TU HUA |
| Applicant returned to address corrections | 1/10/2022 | ZAW HAN |
| Plan Check Approved | 1/31/2022 | ZAW HAN |
| Issued | 2/14/2022 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 12/18/2020 | DANG NGUYEN |
| Address approval | Cleared | 12/28/2020 | ADRIAN CASTRO |
| Permit | Cleared | 12/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 8/23/2021 | ROSE MARIE SMITH |
| Roof/Waste drainage to street | Cleared | 1/4/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/29/2022 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/16/2024 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 2/13/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 6/5/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 9/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 9/4/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/23/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 10/23/2024 | Corrections Issued | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 10/23/2024 | Corrections Issued | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/23/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/5/2024 | Corrections Issued | DAVID MATSON |
| ELECTRICAL-Rough | 11/5/2024 | Approved | DAVID MATSON |
| Green Building Rough | 11/5/2024 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 11/5/2024 | Corrections Issued | DAVID MATSON |
| Verify Sprinkler Sign Off | 11/5/2024 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/2/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 12/2/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/2/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 12/2/2024 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 12/2/2024 | Approved | MATTHEW NELSON |
| Pre-Inspection | 1/2/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/9/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/9/2025 | Approved | MATTHEW NELSON |