8649 N RINCON AVE 91352

Certificate Information: 8649 N RINCON AVE 91352

Application / Permit
20010-10000-03470
Plan Check / Job No.
B20LA18036
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** New 42'-0" x 34'-8" detached, 1-story Accessory Dwelling Unit per LAMC 12.22A.33(c)(d) &(g). All work per Wood Frame Prescriptive Design. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
Issued on 2/14/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/3/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ZAW HAN
Corrections Issued 11/9/2020 ZAW HAN
Quality Review Completed 12/8/2020 TU HUA
Applicant returned to address corrections 1/10/2022 ZAW HAN
Plan Check Approved 1/31/2022 ZAW HAN
Issued 2/14/2022 APPLICANT

Permit Application Clearance Information

Clean Up Green Up Cleared 12/18/2020 DANG NGUYEN
Address approval Cleared 12/28/2020 ADRIAN CASTRO
Permit Cleared 12/28/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/23/2021 ROSE MARIE SMITH
Sewer availability Cleared 8/23/2021 ROSE MARIE SMITH
Roof/Waste drainage to street Cleared 1/4/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2022 Partial Inspection MATTHEW NELSON
Footing/Foundation/Slab 1/16/2024 Partial Inspection MATTHEW NELSON
PLUMBING-Rough 2/13/2024 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 2/16/2024 Approved CHRISTOPHER ROJAS
Pre-Inspection 6/5/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 9/4/2024 Corrections Issued MATTHEW NELSON
Green Building Rough 9/4/2024 Not Ready for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 9/4/2024 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 9/4/2024 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 10/23/2024 Corrections Issued MATTHEW NELSON
Green Building Rough 10/23/2024 Corrections Issued MATTHEW NELSON
Rough-Elec/Plmb/HVAC 10/23/2024 Corrections Issued MATTHEW NELSON
Verify Sprinkler Sign Off 10/23/2024 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 11/5/2024 Corrections Issued DAVID MATSON
ELECTRICAL-Rough 11/5/2024 Approved DAVID MATSON
Green Building Rough 11/5/2024 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 11/5/2024 Corrections Issued DAVID MATSON
Verify Sprinkler Sign Off 11/5/2024 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 12/2/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/2/2024 Approved MATTHEW NELSON
Green Building Rough 12/2/2024 Approved MATTHEW NELSON
HVAC-Rough 12/2/2024 Approved MATTHEW NELSON
PLUMBING-Rough 12/2/2024 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 12/2/2024 Approved MATTHEW NELSON
Pre-Inspection 1/2/2025 Approved MATTHEW NELSON
Drywall Nailing 1/9/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/9/2025 Approved MATTHEW NELSON