1247 S VAN NESS AVE 90019
Certificate Information: 1247 S VAN NESS AVE 90019
- Application / Permit
- 20010-10000-03466
- Plan Check / Job No.
- B20LA18002
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 10/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | DANIEL YIP |
| Corrections Issued | 11/6/2020 | DANIEL YIP |
| Applicant returned to address corrections | 11/16/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 12/15/2021 | JOSEPH RAFOLS |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Issued | 10/13/2022 | APPLICANT |
| Permit Finaled | 10/3/2024 | RUBEN SALAS |
| CofO Issued | 10/3/2024 | RUBEN SALAS |
| Permit Finaled | 10/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| HPOZ | Cleared | 1/15/2021 | AMANDA KAINER |
| Construction near power lines | Cleared | 3/25/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 9/28/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | JEANIE LAM |
| Sewer availability | Cleared | 10/28/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 10/29/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 11/1/2021 | JEANIE LAM |
Contact Information
| Contractor | Pro Renovation Enterprises Inc; Lic. No.: 989072-B | 11306 E 183RD ST STE 204 CERRITOS, CA 90703 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/18/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 11/18/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 11/18/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 12/2/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 12/2/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 12/2/2022 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 12/13/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/27/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 12/27/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Gas Test | 1/3/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Insulation | 1/3/2023 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 1/9/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 1/11/2023 | Corrections Issued | JULIAN AMAYA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 1/31/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/6/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 2/10/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 2/10/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/22/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 2/22/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 2/22/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 3/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 3/28/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 3/28/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/5/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Drywall Nailing | 4/5/2023 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/5/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/5/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Sewer | 4/12/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 5/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 5/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 6/8/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 10/16/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 10/16/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 12/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/19/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 12/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Final | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 12/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 12/19/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 1/26/2024 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 1/26/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/30/2024 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 1/30/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 1/30/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/15/2024 | Corrections Issued | WILLIAM SIERRA |
| Final | 8/15/2024 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Service/Power Release | 8/15/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 8/20/2024 | Conditional Approval | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Approved | WILLIAM SIERRA |
| Service/Power Release | 8/20/2024 | Approved | WILLIAM SIERRA |