630 N LAS CASAS AVE 90272
Certificate Information: 630 N LAS CASAS AVE 90272
- Application / Permit
- 20010-10000-03435
- Plan Check / Job No.
- B20LA17838
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY ADDITION TO EXISTING SFD AND ATTACHED GARAGE
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 10/29/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/26/2020 | PRANITA SHAH |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| Applicant returned to address corrections | 6/2/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/21/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/3/2021 | ARSALAN SHABESTARI |
| Issued | 8/3/2021 | APPLICANT |
| CofO in Progress | 1/30/2024 | EVAN COOPER |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2020 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/15/2020 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/15/2020 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/15/2020 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/15/2020 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 12/15/2020 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 1/16/2021 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | DINAH GARIN |
| Sewer availability | Cleared | 2/26/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 3/2/2021 | MATTHEW CRAIG |
| Coastal Zone | Cleared | 4/23/2021 | DENZEL HENDERSON |
| ZI | Cleared | 4/23/2021 | DENZEL HENDERSON |
| GPI Written Notices | Cleared | 6/2/2021 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 6/2/2021 | ARSALAN SHABESTARI |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 7/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| Underground Mechanical | 7/11/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 7/15/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 7/27/2022 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Corrections Issued | BRENDAN LOONEY |
| Reinforced Concrete Frame | 11/2/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 11/7/2022 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 12/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Wood Construction | 1/19/2023 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 1/19/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/6/2023 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 2/13/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/14/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 2/14/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/17/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 2/17/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 3/2/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 3/28/2023 | Partial Inspection | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 4/3/2023 | Partial Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/15/2023 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 6/21/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/11/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/11/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 7/14/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 7/19/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 7/19/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 7/19/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 12/20/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/20/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/21/2023 | Approved | EVAN COOPER |
| Final | 1/5/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 1/5/2024 | Approved | EVAN COOPER |
| HVAC-Final | 1/5/2024 | Approved | EVAN COOPER |
| Service/Power Release | 1/5/2024 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 1/5/2024 | Approved | EVAN COOPER |
| Final | 1/30/2024 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 1/30/2024 | Approved | EVAN COOPER |