630 N LAS CASAS AVE 90272

Certificate Information: 630 N LAS CASAS AVE 90272

Application / Permit
20010-10000-03435
Plan Check / Job No.
B20LA17838
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO STORY ADDITION TO EXISTING SFD AND ATTACHED GARAGE
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 ARSALAN SHABESTARI
Corrections Issued 10/29/2020 ARSALAN SHABESTARI
Quality Review Completed 11/26/2020 PRANITA SHAH
Building Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 6/2/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 7/21/2021 ARSALAN SHABESTARI
Plan Check Approved 8/3/2021 ARSALAN SHABESTARI
Issued 8/3/2021 APPLICANT
CofO in Progress 1/30/2024 EVAN COOPER
Permit Finaled 3/6/2024 DANIEL ORRANTE
CofO Issued 3/6/2024 DANIEL ORRANTE
Permit Finaled 3/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/15/2020 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 12/15/2020 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 12/15/2020 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 12/15/2020 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 12/15/2020 NIKTA MOUSAVI
BHO/Hillside ordinance Cleared 12/15/2020 NIKTA MOUSAVI
Low Impact Development Cleared 1/16/2021 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 2/10/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 2/25/2021 DINAH GARIN
Sewer availability Cleared 2/26/2021 DINAH GARIN
Hydrant and Access approval Cleared 3/2/2021 MATTHEW CRAIG
Coastal Zone Cleared 4/23/2021 DENZEL HENDERSON
ZI Cleared 4/23/2021 DENZEL HENDERSON
GPI Written Notices Cleared 6/2/2021 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 6/2/2021 ARSALAN SHABESTARI

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2022 Not Ready for Inspection ANDREW NAVE
Footing/Foundation/Slab 7/11/2022 Not Ready for Inspection ANDREW NAVE
Underground Mechanical 7/11/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 7/15/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 7/27/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 10/24/2022 Corrections Issued BRENDAN LOONEY
Reinforced Concrete Frame 11/2/2022 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 11/7/2022 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 12/28/2022 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 1/19/2023 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 1/19/2023 Approved JUAN VALENZUELA
ELECTRICAL-Rough 2/6/2023 Conditional Approval BRENDAN LOONEY
HVAC-Rough 2/13/2023 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 2/13/2023 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 2/14/2023 Corrections Issued BRENDAN LOONEY
Green Building Rough 2/14/2023 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 2/14/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 2/17/2023 Corrections Issued BRENDAN LOONEY
Green Building Rough 2/17/2023 Approved BRENDAN LOONEY
ELECTRICAL-Rough 3/2/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 3/28/2023 Partial Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 4/3/2023 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 4/3/2023 Partial Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 6/15/2023 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 6/21/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/11/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/11/2023 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 7/14/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 7/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 7/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Gas Test 12/20/2023 Approved EVAN COOPER
PLUMBING-Final 12/20/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved EVAN COOPER
ELECTRICAL-Final 12/21/2023 Approved EVAN COOPER
Final 1/5/2024 Corrections Issued EVAN COOPER
Green Building Final 1/5/2024 Approved EVAN COOPER
HVAC-Final 1/5/2024 Approved EVAN COOPER
Service/Power Release 1/5/2024 Not Ready for Inspection EVAN COOPER
Smoke Detectors 1/5/2024 Approved EVAN COOPER
Final 1/30/2024 OK to Issue CofO EVAN COOPER
Service/Power Release 1/30/2024 Approved EVAN COOPER