11443 3/4 W HATTERAS ST 91601
Certificate Information: 11443 3/4 W HATTERAS ST 91601
- Application / Permit
- 20010-10000-03434
- Plan Check / Job No.
- B20LA17833
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD WITH ATTACHED GARAGE AT REAR OF THE LOT 3 of 3
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 6/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 10/6/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/16/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 8/26/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/9/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/19/2022 | SERGIO GUTIERREZ |
| Issued | 1/19/2022 | APPLICANT |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| CofO in Progress | 6/7/2024 | JUAN VALENZUELA |
| Permit Finaled | 6/7/2024 | RUBEN SALAS |
| CofO Issued | 6/7/2024 | RUBEN SALAS |
| Permit Finaled | 6/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/16/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 12/8/2020 | MARKOS PEREZ-BRAN |
| Address approval | Cleared | 3/25/2021 | ADRIAN CASTRO |
| "Q" conditions | Cleared | 3/30/2021 | MAXFIELD VERMY |
| Highway dedication | Cleared | 4/8/2021 | ADRIAN CASTRO |
| Frnt yard landscape/Water mgmt | Cleared | 4/23/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 5/13/2021 | AMMAR ELTAWIL |
| Stormwater Pollution Mitigatn | Cleared | 5/13/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | ADRIAN CASTRO |
| Permit | Cleared | 7/28/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Moving Forward Builders Inc; Lic. No.: 1072204-B | 3219 LIBERTY BLVD SOUTH GATE, CA 90280 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/22/2022 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/18/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 8/31/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 9/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/20/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 9/26/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/14/2022 | No Access for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/17/2022 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/23/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 12/7/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 12/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 12/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 12/7/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 12/13/2022 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 12/13/2022 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/20/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Wood Construction | 12/20/2022 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 12/20/2022 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 12/20/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 12/20/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 12/20/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 12/28/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 12/28/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 12/28/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/23/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 1/23/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/31/2023 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 1/31/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/6/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/6/2023 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/10/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 2/21/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/24/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/24/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/29/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 3/29/2023 | Approved | JACK KARGODORIAN |
| Sewer | 6/20/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Not Ready | KIRK SANDERS |
| Final | 1/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/11/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 1/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/25/2024 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Final | 1/25/2024 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 1/25/2024 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/30/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 1/30/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 1/30/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 3/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Gas Test | 3/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 3/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/18/2024 | No Access for Inspection | KIRK SANDERS |
| Gas Test | 3/18/2024 | No Access for Inspection | KIRK SANDERS |
| HVAC-Final | 3/18/2024 | No Access for Inspection | KIRK SANDERS |
| PLUMBING-Final | 3/18/2024 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 3/21/2024 | Partial Approval | KIRK SANDERS |
| Gas Test | 3/21/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 3/21/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 3/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 4/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 4/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 4/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 4/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 4/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 4/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/19/2024 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/3/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 5/3/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 5/3/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 5/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/3/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/9/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Final | 5/9/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 5/9/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/9/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 5/9/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/10/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 5/10/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/10/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/10/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 5/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 6/7/2024 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 6/7/2024 | Approved | JUAN VALENZUELA |