320 E 118TH ST 90061

Certificate Information: 320 E 118TH ST 90061

Application / Permit
20010-10000-03429
Plan Check / Job No.
B20LA17815
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Proposed 3-car detached garage. 2 of 2
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
CofO Issued on 2/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 MICHAEL LOPEZ
Corrections Issued 10/29/2020 MICHAEL LOPEZ
Quality Review Completed 11/25/2020 PRANITA SHAH
Building Plans Picked Up 12/2/2020 APPLICANT
Plan Check Approved 5/13/2021 MICHAEL LOPEZ
Issued 5/13/2021 APPLICANT
CofO in Progress 7/20/2022 JOHN KLARIN
Permit Finaled 2/1/2023 ANSON MAGLASANG
CofO Issued 2/1/2023 ANSON MAGLASANG
Permit Finaled 2/1/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/15/2020 CECILIO NAVARRO
Low Impact Development Cleared 3/25/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/5/2021 CELINA MORENO
Construction near power lines Cleared 4/15/2021 RIDWAN HARDY

Contact Information

Contractor V C Construction & Development; Lic. No.: 959583-B 24132 MEADOW FALLS DRIVE      DIAMOND BAR, CA 91765
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 2/4/2022 Conditional Approval ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 2/9/2022 Approved JOHN KLARIN
Drywall Nailing 3/3/2022 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 3/7/2022 Partial Approval JOHN KLARIN
Wood Frame 3/17/2022 Approved JOHN KLARIN
Wood Frame 4/13/2022 Approved JOHN KLARIN
PLUMBING-Final 5/12/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/25/2022 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved JOHN KLARIN
BUILDING-Rough-Frame 6/7/2022 Approved JOHN KLARIN
Final 6/7/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 6/7/2022 Approved JOHN KLARIN
Green Building Final 6/7/2022 Approved JOHN KLARIN
Green Building Rough 6/7/2022 Approved JOHN KLARIN
Service/Power Release 6/7/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 6/7/2022 Approved JOHN KLARIN
ELECTRICAL-Final 6/23/2022 Approved JOHN KLARIN
Final 6/23/2022 Corrections Issued JOHN KLARIN
HVAC-Final 6/23/2022 Approved JOHN KLARIN
Service/Power Release 6/23/2022 Not Ready for Inspection JOHN KLARIN
Final 6/30/2022 Corrections Issued JOHN KLARIN
Service/Power Release 6/30/2022 Approved JOHN KLARIN
Final 7/20/2022 OK to Issue CofO JOHN KLARIN