1122 W MARION AVE 90026

Certificate Information: 1122 W MARION AVE 90026

Application / Permit
20010-10000-03428
Plan Check / Job No.
B20LA17822
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED RECREATION ROOM. ***SHALL BE SPRINKLERED PER NFPA 13D*** 1 of 3
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 11/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 MICHAEL LOPEZ
Corrections Issued 10/29/2020 MICHAEL LOPEZ
Quality Review Completed 11/21/2020 PRANITA SHAH
Applicant returned to address corrections 12/3/2020 MICHAEL LOPEZ
Applicant returned to address corrections 5/25/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/26/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/27/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/29/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/18/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/25/2022 MICHAEL LOPEZ
Building Plans Picked Up 1/26/2022 APPLICANT
Applicant returned to address corrections 3/3/2022 MICHAEL LOPEZ
Applicant returned to address corrections 3/4/2022 MICHAEL LOPEZ
Plan Check Approved 3/24/2022 MICHAEL LOPEZ
Issued 5/11/2022 APPLICANT
CofO in Progress 10/23/2023 THOMAS LOGRASSO
CofO Issued 11/2/2023 DEROLD HAUFF
Permit Finaled 11/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 12/14/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 12/14/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 12/14/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 12/14/2020 CELINA MORENO
BHO/Hillside ordinance Cleared 12/14/2020 CELINA MORENO
Highway dedication Cleared 12/14/2020 CELINA MORENO
Permit Cleared 12/14/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/15/2020 CELINA MORENO
Sewer availability Cleared 12/15/2020 CELINA MORENO
Hydrant and Access approval Cleared 1/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 3/25/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/20/2021 CELINA MORENO
Trees in Parkway Cleared 4/27/2021 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 9/30/2021 CHRISTINA PARK
HPOZ Cleared 9/30/2021 CHRISTINA PARK
Miscellaneous Cleared 9/30/2021 CHRISTINA PARK
Miscellaneous Cleared 9/30/2021 CHRISTINA PARK
Miscellaneous Cleared 9/30/2021 CHRISTINA PARK
GPI Written Notices Cleared 1/25/2022 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 1/25/2022 ROBERT HUGHES

Contact Information

Contractor Reuss Alexander Curt; Lic. No.: 637751-B 23777 MULHOLAND HWY SPC #15      CALABASAS, CA 91302
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Reppuhn,, Nikolaus Yongbok; Lic. No.: C83924 1205 DUNNING WAY      SAN DIMAS, CA 91773

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/13/2022 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 6/28/2022 Partial Approval THOMAS LOGRASSO
METHANE-Barrier 6/28/2022 Not Ready for Inspection THOMAS LOGRASSO
METHANE-Subgrade 6/28/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 7/25/2022 Partial Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 8/3/2022 Conditional Approval THOMAS LOGRASSO
Deputy Steel/Welding 8/3/2022 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 9/1/2022 Not Ready for Inspection THOMAS LOGRASSO
METHANE-Barrier 9/1/2022 Not Ready for Inspection THOMAS LOGRASSO
METHANE-Subgrade 9/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 9/15/2022 Corrections Issued THOMAS LOGRASSO
METHANE-Barrier 9/15/2022 Approved THOMAS LOGRASSO
METHANE-Subgrade 9/15/2022 Approved THOMAS LOGRASSO
Deputy Reinf. Concrete 9/20/2022 Conditional Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 10/19/2022 Conditional Approval THOMAS LOGRASSO
Deputy Steel/Welding 10/19/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 1/13/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 1/13/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/14/2023 Corrections Issued THOMAS LOGRASSO
Wood Frame 2/17/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 3/9/2023 Corrections Issued THOMAS LOGRASSO
Green Building Rough 3/9/2023 Approved THOMAS LOGRASSO
MERV13>=Rough 3/9/2023 Approved THOMAS LOGRASSO
METHANE-Rough 3/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 3/9/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/23/2023 Not Ready for Inspection THOMAS LOGRASSO
Insulation 3/23/2023 Conditional Approval THOMAS LOGRASSO
METHANE-Rough 3/23/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 4/10/2023 Approved THOMAS LOGRASSO
Drywall Nailing 4/10/2023 Approved THOMAS LOGRASSO
Insulation 4/10/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/10/2023 Partial Approval THOMAS LOGRASSO
Shower Pan 5/8/2023 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 5/19/2023 Approved CALEB MEISTER
ELECTRICAL-Final 6/27/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 6/27/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 7/5/2023 Partial Approval THOMAS LOGRASSO
HVAC-Final 7/5/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 7/5/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Final 8/8/2023 Approved THOMAS LOGRASSO
Final 8/8/2023 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 8/8/2023 Approved THOMAS LOGRASSO
Green Building Final 8/8/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 8/8/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 8/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 8/8/2023 Approved THOMAS LOGRASSO
Final 10/23/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 10/23/2023 Approved THOMAS LOGRASSO
Service/Power Release 10/23/2023 Approved THOMAS LOGRASSO